Process Phase | Date | Activity | |
---|---|---|---|
Round Zero | |||
Pemex entitlements | August 2014 |
|
|
Round One | |||
Phase One Shallow water exploration |
July 2015 |
|
|
Phase Two Shallow water production | September 2015 |
|
|
Phase Three Onshore production | December 2015 |
|
|
Phase Four Deepwater exploration and extra-heavy oil production | Third quarter 2016 (probable) |
|
|
Phase Five Chicontopec Basin / tight oil | To be determined |
|
|
aIHS Energy, "Mexico: Lessons learned from early auctions drive new approaches for deepwater," Oil and Gas Risk Service (November 20, 2015), https://connect.ihs.com/Document/Show/gi/2852236?connectPath=Search (subscription site). bC. Pascual, IHS Energy, "Mexico's energy reforms: strategic challenges ahead," CERA Special Report (August 2015), https://connect.ihs.com/Document/Show/gi/2823645?connectPath=Search (subscription site). Source: IHS Energy, "Mexico: Lessons learned from early auctions drive new approaches for deepwater," Oil and Gas Risk Service (November 20, 2015), https://connect.ihs.com/Document/Show/gi/2852236?connectPath=Search (subscription site); and C. Pascual, IHS Energy, "Mexico's energy reforms: strategic challenges ahead," CERA Special Report (August 2015), https://connect.ihs.com/Document/Show/gi/2823645?connectPath=Search (subscription site). |