4.1301.5 Cantilevered Floor—Batt Installation

Topic: 
Floors
Subtopic: 
Accessible Floors
Desired Outcome: 
Consistent, uniform thermal boundary Thermal boundary The separation between the interior and exterior environments of a building that slows heat flow between conditioned and unconditioned space to prescribed R-value of an adjoining insulated assembly
TitleSpecification(s)Objective(s)
4.1301.5a
Air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary

Air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary will be installed between joists and sealed

Air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary will be placed to the most interior edge of the top plate of the wall below

Separate cantilevered floor from conditioned floor space

Allow for insulation

4.1301.5b
Installation

Air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary will be insulated between joist from top plate of the wall below to subfloor above

Cantilevered subfloor will be insulated in complete contact with the floor without gaps, voids, compressions, misalignments, or wind intrusions

If kraft-faced batts are used, they will be installed with kraft facing to the air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary

Insulation will be installed to prescribed R-value

Insulate to prescribed R-value

4.1301.5c
Attachment

Batts will be secured with physical fasteners

Ensure insulation remains in contact with subfloor and air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary

4.1301.5d
Exterior soffit

Exterior soffit material will be installed and sealed

Cover and protect insulation

4.1301.5e
Occupant education

A dated receipt signed by the installer will be provided that includes:

  • Coverage area
  • Thickness
  • R-value
  • Document job completion to contract specifications

    Confirm amount of insulation installed

    Comply with 16 CFR 460.17