4.1005.4 Accessible Floors—Loose Fill Over Existing Insulation

Topic: 
Attics
Subtopic: 
Attic Floors
Desired Outcome: 
Insulation controls heat transfer through ceiling
TitleSpecification(s)Objective(s)
4.1005.4a
Preparation

Existing insulation will be in contact with the air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary prior to installing additional insulation on top

Insulation will be adequately marked for depth a minimum of every 300 square feet of attic area, with measurement beginning at the air barrier Air barrier The separation between the interior and exterior environments of a building that slows air flow to the point that no smoke movement is visible at 50 pascals of pressure difference across the boundary

All electrical junction boxes will be flagged to be seen above the level of the insulation

Open electrical junction boxes will have covers installed

Insulation dams and enclosures will be installed as required

Ensure proper performance of insulation Verify uniformity of insulation material Provide location of electrical junctions for future servicing

Prevent an electrical hazard

4.1005.4b
Installation

The correct depth and number of bags will be blown in accordance with manufacturer specifications

Insulation will be installed to prescribed R-value

Insulate to prescribed R-value

4.1005.4c
Safety

Insulation will not be allowed on top of non- IC IC Insulation contact rated can light Can light A light fixture (or can) that is recessed into the ceiling boxes or between a heat-generating appliance and a dam, unless material is rated for contact with heat generating sources

Prevent a fire hazard

4.1005.4d
Onsite documentation

A dated receipt signed by the installer will be provided that includes:

  • Insulation type
  • Coverage area
  • R-value
  • Installed thickness and minimum settled thickness
  • Number of bags installed in accordance with manufacturer specifications
  • Document job completion to contract specifications

    Confirm amount of insulation installed

    Ensure ability to match bags required for total area completed

    Comply with 16 CFR 460.17