Pumped storage projects move water between two reservoirs located at different elevations (i.e., an upper and lower reservoir) to store energy and generate electricity. Generally, when electricity demand is low (e.g., at night), excess electric generation capacity is used to pump water from the lower reservoir to the upper reservoir. When electricity demand is high, the stored water is released from the upper reservoir to the lower reservoir through a turbine to generate electricity. Pumped storage projects are also capable of providing a range of ancillary services to support the integration of renewable resources and the reliable and efficient functioning of the electric grid. View Diagram of a Pumped Storage Project.
![Photo: Ludington Pumped Storage Project, Courtesy: Consumers Energy Company](https://webarchive.library.unt.edu/web/20161225050248im_/https://www.ferc.gov/images/pump-storage-aerial.jpg)
Recent Developments at FERC
The Commission has seen an increase in the number of preliminary permit and license applications filed for pumped storage projects. In 2014, the Commission issued licenses for two proposed pumped storage projects.
Many of the recently proposed pumped storage projects can be classified as using a closed-loop system. We define:
- Closed-loop pumped storage as projects that are not continuously connected to a naturally flowing water feature; and
- Open-loop pumped storage as projects that are continuously connected to a naturally flowing water feature.
Differentiating between open- and closed-loop systems is helpful for illustrating trends in pumped storage project proposals, but project-specific impacts (rather than the open- vs. closed-loop classification) are the primary concern during the licensing process.
Existing and Proposed Projects
To view maps illustrating the location, capacity, and project type (open- vs. closed-loop) of existing and proposed pumped storage projects, see:
- » Licensed Pumped Storage Projects Map
updated 04/01/2016
- » Pending Licenses and Relicenses for Pumped Storage Projects Map
updated 04/01/2016
- » Issued Preliminary Permits for Pumped Storage Projects Map
updated 04/01/2016
- » Pending Preliminary Permits for Pumped Storage Projects Map
updated 04/01/2016
For information on specific projects, including issued licenses and exemptions; pending licenses, relicenses, and exemptions; issued preliminary permits; and pending preliminary permits, see our main Licensing page.