Summary of Compliance Filing Requirements


Deadline
(months after the effective date of the Final Rule)
Compliance Action
Section of Final Rule
October 11, 2012 Submit revised Attachment K of the pro forma OATT and any other Commission jurisdictional documents to include local and regional transmission planning processes that are consistent with the requirements of this Final Rule. Section III A
October 11, 2012 Submit revised Attachment K of the pro forma OATT and other Commission jurisdictional documents to include a cost allocation method for regional cost allocation consistent with principles of this Final Rule. Section III C
July 10, 2013 Submit revised Attachment K of the pro forma OATT and any other Commission jurisdictional documents to include an interregional transmission coordination process consistent with the requirements of this Final Rule. Section IV C
July 10, 2013 Submit revised Attachment K of the pro forma OATT and any other Commission jurisdictional documents to include a cost allocation method for interregional cost allocation consistent with the principles of this Final Rule. Section IV D