Improved Project; National Environmental Policy Act
Appeal Summary | Appeal Letter | Back
Cross-reference: Improved Project; National Environmental Policy Act
Summary: Flooding impacted the State of California in the late winter/early spring of 1998, resulting in major disaster declaration FEMA-1203-DR-CA on February 8, 1998. As a result, the Federal Emergency Management Agency (FEMA) prepared DSR 37461 on February 18, 1999, for $114,731 for the City of San Diego (Applicant) to repair floodwater damage to a paved parking lot, corrugated metal pipe storm drain, earthen embankment, and related facilities in the area of Balboa Park known as Inspiration Point. Included in the DSR was $39,115 in hazard mitigation funding for slope protection, different pipe material, and pipe over sizing. The Applicant claimed an overrun of $71,416 on the final inspection report as a result of improvements and/or project change orders. FEMA prepared DSR 39095 on January 21, 2003, to de-obligate $114,731 because the Applicant did not get prior approval from the Governors Office of Emergency Services (OES) or FEMA for the improved project prior to construction and completion. On April 9, 2003, the Applicant submitted a first appeal seeking reimbursement for $111,359 for the approved scope of work, excluding the additional $74,788 for modifications to the project design it originally claimed. The FEMA Region IX Director denied the appeal on January 18, 2004, because the Applicant did not notify OES or FEMA prior to starting the improved project. Therefore, FEMA did not have the opportunity to review the project for historical and environmental clearances prior to construction. The Applicant submitted its second appeal on March 4, 2004, claiming that the reconstruction of the washed out slope and adjacent parking lot was within the same project area and footprint as the original facility. It stated that only minor changes were made within the parking lot to prevent another overflow in a future disaster. OES supports the Applicants appeal for $111,359.
Issues: Is the improved project eligible for funding?
Findings: No. The Applicant did not notify OES or FEMA prior to construction, precluding OES approval of the improved project and preventing FEMA from completing the necessary National Environmental Policy Act requirements. Therefore, FEMA cannot fund any portion of the work.
Rationale: 44 CFR §206.203(d)(1); 44 CFR Part 10
Second Appeal Summary
FEMA-1203-DR
PA ID# 073-66000; City of San Diego
DSR ID# 37461 & 39095; Improved Project; National Environmental Policy Act
01/25/2005
Citation: FEMA-1203-DR-CA; City of San Diego, Damage Survey Reports (DSRs) 37461, 39095PA ID# 073-66000; City of San Diego
DSR ID# 37461 & 39095; Improved Project; National Environmental Policy Act
01/25/2005
Cross-reference: Improved Project; National Environmental Policy Act
Summary: Flooding impacted the State of California in the late winter/early spring of 1998, resulting in major disaster declaration FEMA-1203-DR-CA on February 8, 1998. As a result, the Federal Emergency Management Agency (FEMA) prepared DSR 37461 on February 18, 1999, for $114,731 for the City of San Diego (Applicant) to repair floodwater damage to a paved parking lot, corrugated metal pipe storm drain, earthen embankment, and related facilities in the area of Balboa Park known as Inspiration Point. Included in the DSR was $39,115 in hazard mitigation funding for slope protection, different pipe material, and pipe over sizing. The Applicant claimed an overrun of $71,416 on the final inspection report as a result of improvements and/or project change orders. FEMA prepared DSR 39095 on January 21, 2003, to de-obligate $114,731 because the Applicant did not get prior approval from the Governors Office of Emergency Services (OES) or FEMA for the improved project prior to construction and completion. On April 9, 2003, the Applicant submitted a first appeal seeking reimbursement for $111,359 for the approved scope of work, excluding the additional $74,788 for modifications to the project design it originally claimed. The FEMA Region IX Director denied the appeal on January 18, 2004, because the Applicant did not notify OES or FEMA prior to starting the improved project. Therefore, FEMA did not have the opportunity to review the project for historical and environmental clearances prior to construction. The Applicant submitted its second appeal on March 4, 2004, claiming that the reconstruction of the washed out slope and adjacent parking lot was within the same project area and footprint as the original facility. It stated that only minor changes were made within the parking lot to prevent another overflow in a future disaster. OES supports the Applicants appeal for $111,359.
Issues: Is the improved project eligible for funding?
Findings: No. The Applicant did not notify OES or FEMA prior to construction, precluding OES approval of the improved project and preventing FEMA from completing the necessary National Environmental Policy Act requirements. Therefore, FEMA cannot fund any portion of the work.
Rationale: 44 CFR §206.203(d)(1); 44 CFR Part 10