4.1.5. Certifications

4.1.5. Certifications

Certifications provide a formal acknowledgment by an approval authority that a system or program meets specific requirements. Certifications, in many cases, are based on statute or regulations and drive systems engineering (SE) planning (i.e., a program may not be able to test or field the capability without certain certifications). Used throughout the acquisition life cycle, certifications reduce program risk and increase understanding of the system. Certain specific certifications are required before additional design, integration, network access, or testing can take place. For example, airworthiness certifications need to be in place before an aircraft can begin flight testing. Often programs insufficiently plan for the number of required certifications. Insufficient planning for certifications can have a negative impact on program costs and schedule.

Obtaining the various certifications can be a lengthy process. As a result, the Program Manager should ensure that the time necessary to obtain any required certification is factored into technical planning. By planning for the activities required to achieve the necessary certifications, the Program Manager and Systems Engineer can ensure that development of the system continues uninterrupted while the program meets all system certification requirements. Early planning allows the Systems Engineer and technical team to begin interacting with certification authorities, which sets the foundation for communication throughout the development of the system.

The SEP Outline requires programs to provide a certification matrix that identifies applicable technical certifications and when they are required during the acquisition life cycle. Programs should include certification activities and events in the Integrated Master Schedule (IMS) and the Integrated Master Plan (IMP).

A non-exhaustive list of certifications is available on the DASD(SE) website. Furthermore, Program Managers and Systems Engineers should consult both Joint and Service-specific domain experts to determine other certifications that may be required.

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/plus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/minus.gif2.0 Overview
https://acc.dau.mil/UI/img/bo/minus.gif2.1. Program Strategies—General
https://acc.dau.mil/UI/img/bo/plus.gif2.2. Program Strategy Document...
https://acc.dau.mil/UI/img/bo/plus.gif2.3. Program Strategy Relationship to...
https://acc.dau.mil/UI/img/bo/plus.gif2.4. Relationship to Request for...
https://acc.dau.mil/UI/img/bo/minus.gif2.5. Program Strategy Classification...
https://acc.dau.mil/UI/img/bo/minus.gif2.6. Program Strategy Document Approval...
https://acc.dau.mil/UI/img/bo/plus.gif2.7. Acquisition Strategy versus...
https://acc.dau.mil/UI/img/bo/minus.gif2.8. Technology Development...
https://acc.dau.mil/UI/img/bo/plus.gif2.8.5. Program Schedule
https://acc.dau.mil/UI/img/bo/plus.gif2.8.7. Business Strategy
https://acc.dau.mil/UI/img/bo/plus.gif2.8.8. Resources
https://acc.dau.mil/UI/img/bo/plus.gif2.8.9. International Involvement
https://acc.dau.mil/UI/img/bo/minus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif3.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif3.1. Life-Cycle Costs/Total Ownership...
https://acc.dau.mil/UI/img/bo/plus.gif3.2. Affordability
https://acc.dau.mil/UI/img/bo/plus.gif3.3. Analysis of Alternatives
https://acc.dau.mil/UI/img/bo/plus.gif3.4. Cost Estimation for Major Defense...
https://acc.dau.mil/UI/img/bo/plus.gif3.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif3.6. Major Automated Information Systems...
https://acc.dau.mil/UI/img/bo/plus.gif3.7. Principles for Life-Cycle Cost...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/minus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif4.1.1. Systems Engineering Policy and...
https://acc.dau.mil/UI/img/bo/minus.gif4.1.2. Systems Engineering Plan
https://acc.dau.mil/UI/img/bo/plus.gif4.1.3. Systems Level Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.1.4. Engineering Resources
https://acc.dau.mil/UI/img/bo/minus.gif4.1.5. Certifications
https://acc.dau.mil/UI/img/bo/minus.gif4.1.6. Systems Engineering Role in...
https://acc.dau.mil/UI/img/bo/minus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.1. Life-Cycle Expectations
https://acc.dau.mil/UI/img/bo/plus.gif4.2.2. Pre-Materiel Development Decision
https://acc.dau.mil/UI/img/bo/plus.gif4.2.3. Materiel Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.4. Technology Development Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.5. Engineering and Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.6. Production and Deployment Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.7. Operations and Support Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.8. Technical Reviews and Audits...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.9. Alternative Systems Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.10. System Requirements Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.11. System Functional Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.12. Preliminary Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.13. Critical Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.14. System Verification...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.15. Production Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.16. Physical Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gif4.2.17. In-Service Review
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/minus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gif6.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif6.1. Total System Approach
https://acc.dau.mil/UI/img/bo/plus.gif6.2 HSI - Integration Focus
https://acc.dau.mil/UI/img/bo/plus.gif6.3. Human Systems Integration Domains
https://acc.dau.mil/UI/img/bo/plus.gif6.4. Human Systems Integration (HSI)...
https://acc.dau.mil/UI/img/bo/plus.gif6.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif6.6. Additional References
https://acc.dau.mil/UI/img/bo/plus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/plus.gif8.0. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif8.1. Threat Intelligence Support
https://acc.dau.mil/UI/img/bo/plus.gif8.2. Signature and other Intelligence...
https://acc.dau.mil/UI/img/bo/plus.gif8.3. Support to the Intelligence...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gif9.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif9.1 OSD T&E Organization
https://acc.dau.mil/UI/img/bo/plus.gif9.2 Service-Level T&E Management
https://acc.dau.mil/UI/img/bo/plus.gif9.3 Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.4 Integrated Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.5 Test and Evaluation Planning
https://acc.dau.mil/UI/img/bo/plus.gif9.6 T&E Reporting
https://acc.dau.mil/UI/img/bo/plus.gif9.7 Special Topics
https://acc.dau.mil/UI/img/bo/plus.gif9.8. Best Practices
https://acc.dau.mil/UI/img/bo/plus.gif9.9. Prioritizing Use of Government Test...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gif10.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif10.1. Decision Points
https://acc.dau.mil/UI/img/bo/plus.gif10.2. Executive Review Forums
https://acc.dau.mil/UI/img/bo/plus.gif10.3. Integrated Product and Process...
https://acc.dau.mil/UI/img/bo/plus.gif10.4. Role of Exit Criteria
https://acc.dau.mil/UI/img/bo/plus.gif10.5. Role of Independent Assessments
https://acc.dau.mil/UI/img/bo/plus.gif10.5.3. Preliminary Design Review (PDR)...
https://acc.dau.mil/UI/img/bo/plus.gif10.6. Information Sharing and DoD...
https://acc.dau.mil/UI/img/bo/plus.gif10.7. Management Control
https://acc.dau.mil/UI/img/bo/plus.gif10.8. Program Plans
https://acc.dau.mil/UI/img/bo/plus.gif10.9. Acquisition Program Baseline (APB)
https://acc.dau.mil/UI/img/bo/plus.gif10.10. Periodic Reports
https://acc.dau.mil/UI/img/bo/plus.gif10.11. Major Automated Information...
https://acc.dau.mil/UI/img/bo/plus.gif10.12. Defense Acquisition Executive...
https://acc.dau.mil/UI/img/bo/plus.gif10.13. Acquisition Visibility
https://acc.dau.mil/UI/img/bo/plus.gif10.14. Special Interest Programs
https://acc.dau.mil/UI/img/bo/plus.gif10.15. Relationship of Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif10.16. Acquisition Program Transition...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gif11.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif11.1. Joint Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.2. International Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.3. Integrated Program Management
https://acc.dau.mil/UI/img/bo/plus.gif11.4. Knowledge-Based Acquisition
https://acc.dau.mil/UI/img/bo/plus.gif11.5. Technical Representatives at...
https://acc.dau.mil/UI/img/bo/plus.gif11.6. Contractor Councils
https://acc.dau.mil/UI/img/bo/plus.gif11.7 Property
https://acc.dau.mil/UI/img/bo/plus.gif11.8. Modeling and Simulation (M&S)...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/minus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/plus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9