Overview
Discretionary & Competitive Federal Grant Program
- Roughly $2.3 billion appropriated each year
- Funds light rail, heavy rail, commuter rail, streetcar, and bus rapid transit projects
FAST outlines: –Multi-year, multi-step process projects must follow to receive funds
- Points during process when FTA must evaluate and rate projects
- Evaluation criteria that must be used
- 5 point scale from low to high for ratings
- Annual Report to Congress that must include ratings for each project and the Administration’s funding recommendations
FAST Eligible Projects
New Starts
- Total project cost is equal to or greater than $300 million or total New Starts funding sought equals or exceeds $100 million
- New fixed guideway system (light rail, commuter rail etc.)
- Extension to existing system
- Fixed guideway BRT system
Small Starts
- Total project cost is less than $300 million and total Small Starts funding sought is less than $100 million
- New fixed guideway systems (light rail, commuter rail etc.)
- Extension to existing system
- Fixed guideway BRT system
- Corridor-based BRT system
Core Capacity
- Substantial corridor-based investment in existing fixed guideway system
- Project must:
- Be located in a corridor that is at or over capactiy or will be in five years
- Increase capacity by 10%
- "not include project elements designated to maintain a state of good repair"
Program of Interrelated Projects
- Program of interrelated projects is the simultaneous development of-
- (A) 2 or more new fixed guideway capital projects, small start projects, or core capacity improvement projects; or
- (B) 2 or more projects that are any combination of new fixed guideway capital projects, small start projects, and core capacity improvement projects.
Bus Rapid Transit categories defined by FAST
Corridor-Based
- Separated right-of-way not required for entirety of corridor
- Makes a substantial investment in a specific corridor
- Defined stations
- Traffic signal priority for buses
- Short headway times
- Bidirectional services for a substantial part of weekdays
Fixed Guideway
- Majority of project operates in a separated right-of-way dedicated for public transportation use
- Makes a substantial investment in a single route within a defined corridor
- Defined stations
- Traffic signal priority for buses
- Short headway times
- Bidirectional services for a substantial part of weekdays & weekend days
Approval Process
New Starts
1) FTA approval: Project Development
- Complete environmental review process including developing and reviewing alternatives, selecting locally preferred alternative (LPA), and adopting it into the fiscally constrained long range transportation plan
2) FTA evaluation, rating, and approval: Engineering
- Gain commitments of all non-5309 funding
- Complete sufficient engineering and design
3) FTA evaluation, rating, and approval: Full Funding Grant Agreement
- Construction
Small Starts
1) FTA Approval: Project Development
- Complete environmental review process including developing and reviewing alternatives, selecting locally preferred alternative (LPA), and adopting it into fiscally constrained long range transportation plan
- Gain commitments of all non-5309 funding
- Complete sufficient engineering and design
2) FTA evaluation, rating, and approval: Construction Grant Agreement
- Construction
Core Capacity
1) FTA Approval: Project Development
- Complete environmental review process including developing and reviewing alternatives, selecting locally preferred alternative (LPA), and adopting it into the fiscally constrained long range transportation plan
2) FTA evaluation, rating, and approval: Engineering
- Gain commitments of all non-5309 funding
- Complete sufficient engineering and design
3) FTA evaluation, rating, and approval: Full Funding Grant Agreement
- Construction
FAST Evaluation and Rating Criteria
New Starts
Project Justification:
- mobility
- environmental benefits
- congestion relief
- economic development
- land use
- cost effectiveness (cost per trip)
Local financial commitment:
- acceptable degree of local financial commitment including evidence of stable and dependable financing sources
Small Starts
Project Justification:
- mobility
- environmental benefits
- congestion relief
- economic development
- land use
- cost effectiveness (cost per trip)
Local financial commitment:
- acceptable degree of local financial commitment including evidence of stable and dependable financing sources
Core Capacity
Project Justification:
- mobility
- environmental benefits
- congestion relief
- economic development
- capacity needs of the corridor
- cost effectiveness (cost per trip)
Local financial commitment:
- acceptable degree of local financial commitment including evidence of stable and dependable financing sources
Funding Recommendations
FTA’s decision to recommend a project for funding in the President’s Budget is driven by a number of factors, including:
- the “readiness” of the project for capital funding
- the project’s overall rating
- geographic equity
- the amount of available funds versus the number and size of the projects in the pipeline
Receipt of Construction Funding
- To receive a construction grant agreement a project must:
- Complete the Planning, Project Development, and Environmental Review Processes
- Meet Project Readiness Requirements (technical capacity, firm and final cost estimate, all funding committed)
- Receive a “medium” or higher overall rating
- Meet all other federal requirements
Updated: Friday, July 8, 2016