U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
This report is an archived publication and may contain dated technical, contact, and link information |
|
Publication Number: FHWA-RD-98-084
|
The information in this manual does not necessarily represent current practice. It is on this site for archival reference purposes only. FHWA Field Manual for Bridge Painting InspectionMaterials/Pre-Painting
Date:_____________ Inspector:__________________
Verification that the paint is not stored in areas subject to temperatures
beyond the recommended limits. ___
Verification that the paint has not exceed its pot life. ___
Documentation of any use of thinner. Do not exceed recommended maximum. ___
Verification of curing time. After painting, inform the contractor of the estimated
time that should be allowed for the paint to cure. Do not allow another coat
to be put on until the appropriate amount of time has elapsed per the existing
weather conditions. ___