Three processes cooperate to deliver capabilities needed by warfighters: the requirements process (JCIDS); the acquisition process (DAS); and the program and budget development process (PPBE). Includes links to DoD and Service policies, guidance, tools, and resources:

Policy

Encyclopedic source of acquisition policy that follows a hierarchy of policy issuance (i.e., executive, legislative, federal, etc.) and filtered according to organization, career field, and special topics.

Communities
of Practice

Links to communities of practice and special interest areas, the latest contribution and discussion posts for open ACC communities, community highlights, and links to related communities.

Training and
Continuous Learning

Information on training and continuous learning that supports DoD acquisition, information that helps manage professional training portfolios, and information on training available from DAU and DoD and Services activities.

Industry

Information on DoD industry partners that helps the participation and execution of DoD processes; including industry support pages, news, information, and links to private sector acquisition contractors.

Applications

AT&L Knowledge Management Systems (AKMS) applications.

 
 

Functional Gateways

Sixteen functional knowledge gateways, one for each of the defense acquisition career fields.

Special Topics

Links to gateways about important topics outside the general portals and beyond the standard career fields:

 

About this page...
This page is the career gateway page for Facilities Engineering professionals. Here you will find information and links related to the Facilities Engineering body of knowledge.
 
For more information, select any of the page thumbnails in the featured web part in the center of the page, or under “Facilities Engineering” in the menu on the top-left.




 

   Home > Skip Navigation LinksAT&L Functional Gateways > Facilities Engineering > Ask A Professor

 

Latest Facilities Questions

Programmatic ESOH Evaluation PESHE
5/20/2016 10:10:00 PM
Question: 1) Is there formal PESHE training within DAU or DoD? 2) Is a weapons systems EMS required if it follow DoDI - to include having a PESHE? 3) Besides the organization's oversight - is there a DoD agency or organization that ensures PESHEs are complete, and of reasonable quality? Who e...(More)


SABER 750K Limit for Maintenance Or Repair
1/27/2016 1:29:00 PM
Question: Can SABER Delivery Orders be greater than $750K if they are only for a maintenance or repair project, and not for new construction? Answer:Readers, the following questions were discussed during off-line communication. 1.  Is this construction inside the U.S. or outside the U.S....(More)


Air Condition replacement.
12/8/2015 11:56:00 AM
Question: Should the local contracting office be the office that fills this requirement for the guest activity? Answer:Normally the local contracting office would have market research associated with the local area as well as the necessary contractual instruments to fulfill the requirements for the...(More)


US Military Personnel on FMS Cases
9/25/2015 4:52:00 PM
Question: When is it appropriate to use US military personnel on FMS cases? Are those billets only used at the SAF level? Answer:In general, it is the joint responsibility of the DoD Component Security Assistance Implementing Activity (IA) and the acquisition command/program management of...(More)


Antideficiency Act grey area clarification
9/4/2015 9:41:00 AM
Question: Does the above scenario violate the Antideficiency act, FAR, or any other US laws? Answer: You do not have a violation of the Anti-deficiency  Act.  What you have is a person who is not a contracting officer directing a contractor to do $24k worth of work.  Only a Contract...(More)


Communication with Offerors after Receipt of Proposals
7/13/2015 1:42:00 PM
Question: 1. If you give one vendor an opportunity to change their proposal, do you have to give them all an opportunity? 2. Does it matter if you are using simplified acquisitions procedures, GSA or GWAC contract? Answer:There is a GWAC guide you might find very helpful.  The GWAC order...(More)


What Color funding can I use to purchaseBack-up Generators
3/19/2015 5:05:00 PM
Question: My question is what color funding can I use to purchase generators and what regulation tells what I need to use? Answer:It appears your question revolves around the use of Procurement funds or O&M funds to purchase backup generators which are as stated real property.  The Federal ...(More)


Is personal health insurance allowable for a one-person startup?
1/15/2015 10:12:00 AM
Question: Question 1: Is the health insurance expense allowable? I feel it is different than a group health insurance plan a corporation would hold for it's employees. In that case, in my opinion, it is a necessary cost of doing business. In the current scenario, I do not feel that the cost is be...(More)


MILCON Information Assurance Requirements
12/8/2014 3:32:00 PM
Question: Is there a checklist or applicable milestone entry/exit criteria that exists for IA requirements when building a new MILCON facility? Answer:   (1)  I was unable to find a checklist or applicable milestone entry/exit criteria for IA requirements when building a new MILCO...(More)


Design Build
5/9/2014 7:58:00 AM
Question: Can this project go out as a design build if all we want is the plans updated? Does it qualify as a design build if we already paid for the design once? Answer:This does not sound like a design-build project as envisioned by FAR 36.3 in so far as you indicate the agency desire to use the ...(More)