Title - Army Cost position and the Independent Cost Estimate.

Question -

Is the program required to change the APB to reflect the lower estimate from the ICE?

Scenario - 1. Army cost position completed and approved 2. ICE is completed and significantly lower than ACP 3. APB has been completed and approved according to ACP 4. Milestone C has been approved

Posted - 9/23/2016 3:56:00 PM

Subject Area - Program Management


 
 

A picture of an A. The text to the right is the answer.

Based on the background information provided, it would seem that the question is overcome by events since MS C "has been approved."  The MDA would have approved of the cost estimate and the DCAPE would have coordinated on it before the ADM was signed.  The APB would be updated to reflect the most recent and aggreed upon/coordinated information.  Below is some guidance excerpted from the DAG, Chapter 3. I hope this helps.

3.4.3.1. Cost Assessment Reviews (Pre-Milestone Decisions and Full-Rate Production)

The Office of Cost Assessment (CA), within the Office of Cost Assessment and Program Evaluation (CAPE), receives the results of and reviews all cost estimates and cost analyses and associated studies conducted by the DoD Components for major defense acquisition programs (MDAPs) and major automated information system (MAIS) programs and has timely access to any records and data in the Department.

During the CA review process, CA staff may engage in discussion with the DoD Components regarding any discrepancies related to the cost estimates and comment on deficiencies regarding the methodology or execution of cost estimates. Furthermore, the Director, CAPE, is authorized to concur with the choice of a cost estimate used to support the acquisition program baseline (APB).

3.4.3.1.5. Cost Assessment Review Events—3 Days before Overarching Integrated Product Team (OIPT) Meeting

Cost Assessment (CA) staff's final report is delivered to the OIPT leader at least three days before the OIPT meeting. Immediately thereafter, it is distributed to the OIPT members and is available to the DoD Component staff. The expectation is that any issues had already emerged in prior discussions and that the final CA report should not contain any surprises. The report normally is two to three pages and typically includes the following: •Summary of DoD Component Cost Estimate
•Summary of Cost Assessment independent cost estimate
•Comparison or reconciliation of the two estimates
•Assessment of program risks
•Comparison of (time-phased) Cost Assessment cost estimate to current program funding
•Recommendations concerning program funding



Rate this answer - Was this answer helpful?:

Enter above code
 
 
       
 
   
 
       

Warnings and Disclaimers

DISCLAIMER: The information contained with�in this server is not official United States Government policy and cannot be construed as official in any way.

NOTICE: Unauthorized attempts to upload information or change information on this service are strictly prohibited and may be punishable under the Computer Fraud and Abuse Act of 1986. All information contained within this server is considered public information and may be distributed or copied. Anyone using this system consents to monitoring of this use by system or security personnel.

DISCLAIMER OF LIABILITY: With respect to documents available from this server, the United States Government nor any of their employees, makes any warranty, express or implied, including the warranties of merchantability and fitness for a particular purpose, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights.

DISCLAIMER OF ENDORSEMENT:
Reference herein to any specific commercial products, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government. The views and opinions of authors expresses herein do not necessarily state or reflect those of the United States Government, and shall not be used for advertising or product endorsement purposes.

Submit Feedback

Your feedback on the quality of the AAP service is important to us. Please take our survey to help us improve the AAP in the future.

 

Sign In