P3 Defined

Design Build Operate Maintain [ New Build Facilities ]

P3 Graphic Defined

Detailed description of the graphic

Public Owner/Financier (state or local government, through equity or debt) combines procurements for private Engineer and Contractor (and Contractor's Operator) into a single contract.

The design-build-operate-maintain (DBOM) model is an integrated partnership that combines the design and construction responsibilities of design-build procurements with operations and maintenance. These project components are procured from the private sector in a single contract with financing secured by the public sector. This project delivery approach is also known by a number of different names, including "turnkey" procurement and build-operate-transfer (BOT).

Responsibilities

With a DBOM contract, a private entity is responsible for design and construction as well as long-term operation and/or maintenance services. The public sector secures the project's financing and retains the operating revenue risk and any surplus operating revenue.

Advantages

The advantage of the DBOM approach is that it combines responsibility for usually disparate functions - design, construction, and maintenance - under a single entity. This allows the private partners to take advantage of a number of efficiencies. The project design can be tailored to the construction equipment and materials that will be used. In addition, the DBOM team is also required to establish a long-term maintenance program up front, together with estimates of the associated costs. The team's detailed knowledge of the project design and the materials utilized allows it to develop a tailored maintenance plan that anticipates and addresses needs as they occur, thereby reducing the risk that issues will go unnoticed or unattended and deteriorate into much more costly problems.

LifeCycle Costing

The benefits of "lifecycle costing" are particularly important, as most infrastructure owners spend more money maintaining their systems than on expansion. In addition, the lifecycle approach removes important maintenance issues from the political vagaries affecting many maintenance budgets, with owners often not knowing how much funding will be available to them from year to year. In such cases, they are often forced to spend what money they do have on the most pressing maintenance needs rather than a more rational and cost-effective, preventive approach.

Procurement Process

Owners award DBOM contracts by competitive bid following a transparent tender process. Proposers respond to the specifications provided in the tender documents and are usually required to provide a single price for the design, construction, and maintenance of the facility for the time period specified. Proposers are also required to submit documentation on their qualifications, thereby allowing owners to compare the costs of the different offers and the ability of the proposers to meet their specified needs.

Standard Specifications

While the potential exists to reap substantial rewards by utilizing the integrated DBOM approach, owners who are not accustomed to this approach must take great care to specify all standards to which they want their facilities designed, constructed, and maintained. With a DBOM procurement, owners relinquish much of the control they typically possess with more traditional project delivery. Unless needs are identified up front as overall project specifications, they will not generally be met. This is important, because from design through operation, DBOM contracts can extend for periods of up to 20 years or more.

Projects