Currently Open Recommendations
|
P-01-02 |
South Riding - Pipeline Technology (Excess Flow Valves); OAA
|
Jun 22, 2001 |
|
P-09-02 |
ERW Study Implementation; OAA |
Oct 27, 2009 |
|
P-11-08 |
PG&E Rupture - Providing System-Specific Information; OAA |
Sep 26, 2011 |
|
P-11-09 |
PG&E Rupture - Immediate 911 Notifications; OAA |
Sep 26, 2011 |
|
P-11-10 |
PG&E Rupture - Equipping SCADA Systems; OAA |
Sep 26, 2011 |
|
P-11-11 |
PG&E Rupture - Installing ACVs or RCVs; OAA |
Sep 26, 2011 |
|
P-11-12 |
PG&E Rupture - Eliminating Operator Discretion; OAA |
Sep 26, 2011 |
|
P-11-14 |
PG&E Rupture - Eliminating Grandfather Clause; OAA |
Sep 26, 2011 |
|
P-11-15 |
PG&E Rupture - Post-Construction Hydrostatic Pressure Test; OAA |
Sep 26, 2011 |
|
P-11-18 |
PG&E Rupture - Revision of Integrity Management Protocol; OAA |
Sep 26, 2011 |
|
P-11-20 |
PG&E Rupture - Meaningful Metrics; OAA |
Sep 26, 2011 |
|
P-12-3 |
Enbridge - Engineering Assessment of Cracks; OAA |
Jul 25, 2012 |
|
P-12-4 |
Revising the "discovery of condition"; OAA |
Jul 25, 2012 |
|
P-12-7 |
Enbridge - Team Training; OAA |
Jul 25, 2012 |
|
P-12-8 |
Enbridge - Extend OQ Requirements to Control Center Staff; OAA |
Jul 25, 2012 |
|
P-12-9 |
Enbridge - Harmonize OSR Planning Requirements; OAA |
Jul 25, 2012 |
|
P-14-01 |
Sissonville – Add Principal Roadways to HCA Requirements; OAA |
Mar 5, 2014 |