Monthly project statistics, frequently asked questions, outage schedule, project standing orders, discharge measurements, boat ramp elevations, etc.
-
Post 2011 Flood Event Analysis of Mainstem Flood Control Storage.
-
Annual Operating Plan Public Meetings - Presentation
-
Story boards for Annual Operating Plan public meetings
|
The U.S. Army Corps of Engineers Missouri River Basin Water Management Division plans to step up Gavins Point dam releases by 4,000 cubic feet per second this week in response to colder temperatures moving into the region. We will monitor the situation closely and make additional adjustments if necessary to maintain intakes along the lower river. [Read More]
Published: Dec-18-12
Gavins Point releases are currently being stepped down to minimum winter release levels as drought conditions persist throughout the Missouri River basin. Releases from Gavins Point will continue to be gradually reduced and will be targeted at the minimum level of 12,000 cfs this winter to conserve water in the reservoir system. [Read More]