everglades photosThe first increment of the G-3273 and S-356 Pump Station Field Test is currently under development. This is the first step in the incremental approach to develop the final operating plan for the Modified Water Deliveries to Everglades National Park and C-111 South Dade projects.

The first increment of this test will evaluate the raising or removing of the G-3273 constraint of 6.8 feet and holding the L-29 Canal stage at 7.5 feet to enable increased water deliveries to Everglades National Park.

 Read more about the field test here.

What's New

PROJECT DELIVERY TEAM MEETING:  August 30, 2016

Project Delivery Team (PDT) meetings enable federal, state and local agencies and tribal governments to provide their input into the first increment of the G-3273 and S-356 Pump Station Field Test. Members of the public may attend PDT meetings and provide public comment both during and at the end of the meeting.


August 30, 2016 - Project Delivery Team Meeting
1:00 PM - 4:30 PM (ET)
South Florida Water Management District (SFWMD) Governing Board Auditorium (B-1 Building), 3301 Gun Club Road, West Palm Beach, FL 33406

The meeting will also be available via teleconference and web meeting:

Call-in number:

USA Toll-Free: (877) 848-7030
Access Code: 3753824
Security Code: 1234

Web Meeting Address:

https://www.webmeeting.att.com
Meeting Number: (877) 848-7030
Access Code: 3753824
Security Code: 1234

* The first time you use the Web Meeting Service, you will need to download the client software. Web Meeting HELP & Software Downloads can be found at: https://www.webmeeting.att.com *
 
Meeting Documents:


Water operations field test begins in Everglades - Oct. 15, 2015

The first increment of the G-3273 and S-356 Pump Station Field Test (Increment 1) started today. This incremental water operations field test has been initiated to take a deeper look at what operational refinements are possible to provide additional ecological benefits to the Everglades ecosystem.  The test aims to increase flows to Everglades National Park and is the result of a collaborative effort between the U.S. Army Corps of Engineers, U.S. Department of the Interior and the State of Florida.


ENVIRONMENTAL ASSESSMENT & FINDING OF NO SIGNIFICANT IMPACT 

The Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) for the first increment of the G-3273 and S-356 Pump Station Field Test are now available online.

The first increment of the G-3273 and S-356 pump station field test will evaluate the raising or removing of the G-3273 constraint of 6.8 feet and holding the L-29 Canal stage at 7.5 feet to enable increased water deliveries to Everglades National Park. This is the first step in the incremental approach to develop the final operating plan for the Modified Water Deliveries to Everglades National Park and C-111 South Dade projects.

The EA and Draft FONSI were available for public and agency review through April 5, 2015.  Comments received during this 60-day comment period were taken into consideration as the report was finalized.

Additional information on the field test available here.

PDT Meetings

PROJECT DELIVERY TEAM MEETINGS

Project Delivery Team (PDT) meetings enable federal, state and local agencies and tribal governments to provide their input into the first increment of the G-3273 and S-356 Pump Station Field Test. Members of the public may attend PDT meetings and provide public comment both during and at the end of the meeting.  


Jan. 27, 2016 - Project Delivery Team Meeting
1:30 PM - 4:45 PM (ET)
South Florida Water Management District (SFWMD) Governing Board Auditorium (B-1 Building), 3301 Gun Club Road, West Palm Beach, FL 33406

Meeting Documents:


June 30, 2015 - Project Delivery Team Meeting
10 AM - 2 PM (ET)
South Florida Water Management District (SFWMD) Miami Field Station, 9001 NW 58th Street Miami, FL 33178

 Meeting Documents:


 December 9, 2014 - Project Delivery Team Meeting
1:30 PM - 5:30 PM (ET)
South Florida Water Management District (SFWMD) Bill Storch Room (B-1 Building), 3301 Gun Club Road, West Palm Beach, FL 33406

 Meeting Documents:


October 15, 2014 - Project Delivery Team Meeting
9:30 AM - 3:30 PM (ET)
South Florida Water Management District (SFWMD) Governing Board Auditorium (B-1 Building), 3301 Gun Club Road, West Palm Beach, FL 33406

Meeting Documents:


September, 3, 2014 - Project Delivery Team Meeting
9:30 AM - 4:00 PM (ET)
South Florida Water Management District (SFWMD) Miami Field Station, 9001 NW 58th Street Miami, FL 33178

Meeting Documents:


July 16, 2014 - Project Delivery Team Meeting
9:30 AM - 12 PM (ET)
South Florida Water Management District (SFWMD) Fort Lauderdale Field Station, 2535 Davie Road, Davie, FL 33317

Meeting Documents: