Albeni Falls Dam
2376 E. Highway 2
Oldtown, ID 83822

208-437-3133

Like us!

 

 

Albeni Falls Dam

Albeni Falls DamAlbeni Falls Dam was authorized for construction under the Flood Control Act of 1950. This Act was signed by the United States Congress in response to a great flood that swept over the river valleys of the Columbia basin in 1948. Albeni Falls Dam was built from January 1951 to December of 1955 at a total cost of $34 million.

The dam is made up of two different parts: the powerhouse and the spillway. The powerhouse contains powerful turbines and generators that convert gravity-driven river water into hydroelectricity. The spillway can either store water for downstream power production and irrigation at other dams along the Pend Oreille and Columbia Rivers, or release water for upstream flood control. There is 136,000 cubic yards (61 million pounds) of concrete in the structure.

Today, it produces over 200 million kilowatt hours of electrical energy each year. When running at top capacity, the three Kaplan generators can generate 42.6 megawatts. That's enough power to supply about 15,000 homes. Bonneville Power Administration markets this electricity to customers primarily in the Pacific Northwest. This power production saves the United States from buying about 4.9 million barrels f imported oil each year.

Lake Pend Oreille (Ponderay)

Lake Pend Oreille is one of the largest and deepest natural lakes in North America. Spanning near 150 square miles, it extends through a glacially carved, U-shaped valley that separates three lofty mountain ranges-the Cabinets, Selkirks and Coeur d’ Alenes. Rimmed by these mountains that rise over 6,500 feet, the lake’s average depth is 545 feet, but in some areas plunges to a depth of 1,237 feet.

The shoreline of the combined Lake Pend Oreille and the Pend Oreille River is 226 miles. It’s length 68 miles, with a maximum width of 6 ½ miles.

The name “Pend Oreille” derives from the French name for a local tribe of Indians that wore pendant ornaments in their earlobes.

Flow Update

Sept. 27, 2016

Lake Pend Oreille elevation at Hope Gauge: 2,061.6 feet
Albeni Falls Dam inflow: ~13,500 cubic feet per second
Albeni Falls Dam outflow: 18,000 cfs 

Outflow from Albeni Falls Dam will increase from 18,000 to 23,000 cfs today starting at 9:30 a.m. PST.

The current operation is to draft to an end of September elevation of 2,061 ft, as measured at the Hope gage.

Short term modeling forecasts are provided by the Northwest River Forecast Center.  Their projections for Albeni Falls Dam inflow, outflow and the Lake Pend Oreille at the Hope gage can be found here: http://www.nwrfc.noaa.gov/river/station/flowplot/flowplot.cgi?lid=ALFW1

Projections for future operations at Albeni Falls Dam can be found here: http://www.nws.usace.army.mil/About/Offices/Engineering/HydraulicsandHydrology/OperationalProjections.aspx

Page 1 shows Lake Pend Oreille Elevation at the Hope gauge
Page 2 shows Albeni Falls Dam inflow
Page 3 shows Albeni Falls Dam outflow