Only those products changed as a result of the 2016 SSRAC Meeting have been posted.  These documents are PRELIMINARY and are not intended for immediate distribution or invocation, nor do they authorize any change in terms, conditions, delivery schedule, price, or amount of any existing Government contract.

 Please review these products and provide any comments you may have NLT 18 OCT 2016, using the Preliminary Review Comment form.  COMMENTS WILL ONLY BE ACCEPTED USING THIS FORM. Please complete, attach, and e-mail preliminary comment forms to SSRAC@navy.mil. 

 

NAVSEA STANDARD ITEMS

 

ITEM NO.

 

 

TITLE

UTILIZATION

CATEGORY

 

 

DATE

009-01

General Criteria; accomplish

I

 

xx NOV 2016

009-02

Environmental Compliance Reports for Material Usage at Naval Facility; accomplish

I

 

xx NOV 2016

009-03

Toxic and Hazardous Substances; control

I

 

xx NOV 2016

009-04

Quality Management System; provide

I

 

xx NOV 2016

009-05

Temporary Accesses; accomplish

II

 

xx NOV 2016

009-06

Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish

I

 

xx NOV 2016

009-07

Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish

I

 

xx NOV 2016

009-08

Fire Protection at Contractor's Facility; accomplish

I

 

xx NOV 2016

009-09

Process Control Procedure (PCP); provide and accomplish

II

 

xx NOV 2016

009-10

Asbestos-Containing Material (ACM); control |

I

 

xx NOV 2016

009-11

Insulation and Lagging; accomplish |

II

 

xx NOV 2016

009-12

Weld, Fabricate, and Inspect; accomplish |

II

 

xx NOV 2016

009-13

Meter; repair |

II

 

xx NOV 2016

009-14

Gage, Switch, and Thermometer; repair|

II

 

xx NOV 2016

009-15

Rotating Machinery; balance

II

 

xx NOV 2016

009-16

Electronic Equipment; repair

II

 

xx NOV 2016

009-17

Rotating Electrical Equipment; repair

II

 

xx NOV 2016

009-18

Magnetic Material; control

II

 

xx NOV 2016

009-19

Provisioning Technical Documentation (PTD); provide

I

 

30 JUL 2015

009-20

Government Property; control

I

 

18 JUL 2014

009-21

Logistics and Technical Data; provide

I

 

18 JUL 2014

009-22

Canceled xx NOV 2016

 

 

 

009-23

Interference; remove and install|

I

 

xx NOV 2016

009-24

Shipboard Authorization, Control, Isolation, Blanking, Tagging and Cleanliness Requirements; accomplish

I

 

xx NOV 2016

009-25

Structural Boundary Test; accomplish

II

 

xx NOV 2016

009-26

Deck Covering; accomplish

II

 

xx NOV 2016

009-27

Material Identification and Control (MIC) for Level I System; accomplish |

II

 

xx NOV 2016

009-28

Fire Prevention; accomplish |

I

 

xx NOV 2016

009-29

Asbestos‑Free Pipe Hanger Liner Material; install

I

 

29 JUL 2004

009-30

Boiler Sample Tube; inspect |

II

 

xx NOV 2016

009-31

Boiler Waterjet Cleaning; accomplish

II

 

18 JUL 2014

009-32

Cleaning and Painting Requirements; accomplish

II

 

xx NOV 2016

009-33

Rotating Electrical Equipment; rewind

II

 

xx NOV 2016

009-34

Fire Protection of Unmanned Vessels at Contractor's Facility; accomplish

I

 

xx NOV 2016

009-35

Canceled xx NOV 2016

 

 

 

009-36

Controller; repair

II

 

xx NOV 2016

009-37

General Procedures for Woodwork; accomplish

II

 

xx NOV 2016

009-38

Boiler, Catapult Accumulator, and Reboiler Dry Lay-up; accomplish

II

 

xx NOV 2016

009-39

Technical Manual Contract Requirement (TMCR) for a New Technical Manual for Commercial Equipment/Component; accomplish

I

 

xx NOV 2016

009-40

Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a Naval Facility; provide |

I

 

xx NOV 2016

009-41

Technical Manual Contract Requirement (TMCR) for a Topically Structured Technical Manual; accomplish

II

 

xx NOV 2016

009-42

Technical Manual Contract Requirement (TMCR) for Updating Technical Manual; accomplish

II

 

xx NOV 2016

009-43

Engineering Plant Production Completion Date (PCD), Light-Off Assessment (LOA) Support; provide

II

 

30 JUL 2015

009-44

Cancelled 18 JUL 2014

 

 

 

009-45

Tapered Plug Valve; repair

II

 

xx NOV 2016

009-46

Butterfly Valve, Synthetic and Metal Seated; repair

II

 

18 JUL 2014

009-47

Gate Valve; repair

II

 

xx NOV 2016

009-48

Pressure Seal Bonnet Valve Shop | Repair; accomplish

II

 

xx NOV 2016

009-49

Pressure Seal Bonnet Valve In-line Repair; accomplish

II

 

xx NOV 2016

009-50

Horizontal Swing Check Valve; repair

II

 

xx NOV 2016

009-51

Globe, Globe Angle, and Globe Stop Check Valve; repair

II

 

xx NOV 2016

009-52

Relief Valve; repair

II

 

xx NOV 2016

009-53

Bolted Bonnet Steam Valve Shop Repair; accomplish

II

 

xx NOV 2016

009-54

Bolted Bonnet Steam Valve In-line Repair; accomplish

II

 

xx NOV 2016

009-55

Regulating/Reducing Valve; repair

II

 

xx NOV 2016

009-56

Main Propulsion Boiler Wet Lay-up; accomplish

II

 

xx NOV 2016

009-57

Reduction Gear Security; | accomplish

II

 

xx NOV 2016

009-58

Pump and Driver Shaft Alignment; accomplish

II

 

01 SEP 2015

009-59

Organotin Antifouling Material; control

II

 

xx NOV 2016

009-60

Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration; provide and manage

I

 

01 SEP 2015

009-61

Shipboard Use of Fluorocarbons; control

I

 

18 JUL 2014

009-62

Boiler Handhole, Manhole Seat and Plate; inspect |

II

 

xx NOV 2016

009-63

Lubricating Oil and Hydraulic Fluid; analyze |

II

 

xx NOV 2016

009-64

Synthetic Fire Resistant Hydraulic Fluid; control

II

 

xx NOV 2016

009-65

Polychlorinated Biphenyls (PCBs); control

I

 

29 JUL 2011

009-66

Cancelled 18 JUL 2014

 

 

 

009-67

Integrated Total Ship Testing; manage

I

 

xx NOV 2016

009-68

Bolted Bonnet Valve; repair

II

 

29 JUL 2011

009-69

Heavy Weather/Mooring Plan; provide

I

 

30 JUL 2015

009-70

Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish

I

 

xx NOV 2016

009-71

Piping Systems; test |

II

 

xx NOV 2016

009-72

Physical Security at a Private Contractor Facility; accomplish |

I

 

xx NOV 2016

009-73

Shipboard Electrical/Electronic

Cable Procedure; accomplish

I

 

xx NOV 2016

009-74

Occupational, Safety and Health Plan; accomplish

I

 

xx NOV 2016

009-75

Circuit Breaker; repair

II

 

xx NOV 2016

009-76

Waveguide and Rigid Coaxial Lay-Up; accomplish

II

 

xx NOV 2016

009-77

Cofferdam Installation; accomplish

II

 

xx NOV 2016

009-78

Passive Countermeasures System (PCMS) Material; repair |

II

 

xx NOV 2016

009-79

Government Owned Material (GOM) Status; report

I

 

xx NOV 2016

009-80

Ship Facilities; maintain

I

 

xx NOV 2016

009-81

Compartment Closeout; accomplish

I

 

xx NOV 2016

009-82

Installation of Equal Component | Vice Specified Component; report

I

 

xx NOV 2016

009-83

Wire Rope Assembly; fabricate |

II

 

xx NOV 2016

009-84

Threaded Fastener Requirements; accomplish

II

 

xx NOV 2016

009-85

Government Sponsored Planning Yard/Configuration Data Manager (CDM) On-Site Representative Facility; provide

II

 

19 JUL 2007

009-86

Recovery and Turn-In of Ozone Depleting substance (ODS); accomplish

II

 

xx NOV 2016

009-87

Chemical Disinfection Procedures; accomplish

II

 

xx NOV 2016

009-88

Collection, Holding and Transfer (CHT) and Motor Gasoline(MOGAS) Tanks, Spaces, and Piping, including Sewage or MOGAS-Contaminated Tanks, Spaces, and Piping; certify

II

 

xx NOV 2016

009-89

Contractor Furnished Anodes(Purchase and Inspect); accomplish

I

 

xx NOV 2016

009-90

Technical Representative; provide

II

 

18 JUL 2014

009-91

Propeller In-Place Inspection; accomplish

II

 

xx NOV 2016

009-92

Resilient Mount; install |

II

 

xx NOV 2016

009-93

Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide

I

 

xx NOV 2016

009-94

General Environmental Work at Contractor Facility; accomplish |

I

 

xx NOV 2016

009-95

Mechanically Attached Fittings (MAFs) for Piping Systems; install

II

 

xx NOV 2016

009-96

Ball Valve; repair

II

 

xx NOV 2016

009-97

Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide

I

 

17 JAN 2013

009-98

Canceled xx NOV 2016

 

 

 

009-99

Ship Departure Report; provide

I

 

18 JUL 2014

009-100

Ship's Stability; maintain |

I

 

xx NOV 2016

009-101

Ships Transit and Berthing; accomplish

I

 

xx NOV 2016

009-102

Alteration Verification; provide

I

 

29 JUL 2011

009-103

Weight and Moment Change Data; provide

I

 

18 JUL 2014

009-104

Vibration Testing and Analysis; accomplish

II

 

18 JUL 2014

009-105

Thermal Sprayed Coatings for Machinery Component Repair; accomplish

II

 

xx NOV 2016

009-106

Work Authorization Form Coordinator (WAFCOR); provide

I

 

xx NOV 2016

009-107

Piping System Cleanliness Restoration (Non-Nuclear); accomplish

II

 

xx NOV 2016

009-108

Aircraft Carrier Transit and Berthing; accomplish

I

 

xx NOV 2016

009-109

Non-SUBSAFE Work on SUBSAFE-Certified Vessels; accomplish |

I

 

xx NOV 2016

009-110

Non-Nuclear Work on a Nuclear Vessel; accomplish |

I

 

xx NOV 2016

009-111

Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage

I

 

xx NOV 2016

009-112

Prevention of Radiographic-Inspection Ionizing-Radiation Hazard; accomplish |

 

II

 

xx NOV 2016

009-113

Rotating Electrical Equipment with a Sealed Insulation Systems (SIS); rewind

II

 

xx NOV 2016

009-114

Mold Remediation; accomplish

II

 

07 NOV 2013

009-115

Bearing Rebabbitting; accomplish

II

 

30 JUL 2015

009-116

Auxiliary and Waste Heat Boiler Sodium Nitrite Wet Lay-up; accomplish

II

 

30 JUL 2015

009-117

Combat Systems Light-Off; support

I

 

xx NOV 2016

009-118

CG Deck Loading; accomplish

I

 

18 JUL 2014

009-119

Cancelled 18 JUL 2014

 

 

 

009-120

Fact Finding and Critique of Unplanned Event; manage |

I

 

xx NOV 2016

009-121

Ship Assessment/Inspection; | accomplish

II

 

xx NOV 2016

009-122

Temporary Padeye; install and removal

I

 

xx NOV 2016

009-123

Fiber Optic System; remove, relocate, repair, and install

I

 

xx NOV 2016