The Lufkin US 59 North/Loop 287 project will cover an area of US 59 from State Highway (SH) 103 East to just north of Farm to Market (FM) 3439 (Spence Street).

Purpose

This three-phase project will allow traffic on US 59, US 69 and Loop 287 to flow freely through the US 59 North at Loop 287 intersection and will improve clearances at the bridges.

Project Status

The Phase One project is under construction.

Phase Two is not funded.

Phase Three is funded. Construction is planned to begin in the fall of 2014.

  • Construct new underpass at Business 59 (Timberland Drive) and the Angelina Neches River Railroad crossing.