SH 249 - Todd Mission to Navasota

The purpose of this project is to identify a potential route or routes for SH 249 between Todd Mission and Navasota.

A recommended study area for the proposed project was presented at an open house in October 2013. More than 230 people attended and we received over 40 comments. Based on comments from the open house, TxDOT identified additional environmental constraints for design considerations. An evaluation process was started to identify and compare potential routes with the project purpose and needs.

Six alternatives were presented at the open house on April 3, 2014. Alignment B3 was recommended to be compared to the no-build alternative. After considering comments and input received during the study, a hybrid alignment combining alternatives B and C is now preferred. This preferred alignment will be presented at a public hearing in summer 2015.

Benefits

The proposed improvements are expected to provide the following, as outlined in the purpose and needs identified by the SH 249 Working Group:

  • Improve safety: Crash rates on FM 1774 and SH 105 exceed the statewide average
  • Address traffic growth: Since 1980, traffic has increased 274 percent on FM 1774 and 197 percent on SH 105 
  • Improve regional connections: Provide transportation system continuity to surrounding area
  • Address evacuation needs: Increase evacuation capacity during emergencies

Get Involved

Next Steps

  • Public Hearing - Summer 2015
  • Environmental Decision - Anticipated Summer 2015
  • Construction - Estimated Fall 2015

Downloads

Contact Us

Director of Transportation Planning and Development
TxDOT Bryan District
2591 N. Earl Rudder Freeway
Bryan, TX 77803

Phone: (979) 778-9727
Fax: (979) 778-9702
Email

Subscribe to Updates