Director, Office
of Science (SC Director) (SC-1) |
Approval
Authority for Hazard Category 1, 2, and 3 nuclear facilities safety basis
documentation has been specifically delegated in writing to the Deputy Director
for Field Operations (DDFO) (SC-3) per January 26, 2012 memorandum from the SC Director.
Some additional delegations have been made to Site Office Managers beyond SC-3. See current delegations at http://scms.sc.doe.gov/Reports/DelegationsList.cfm
-
Approves exemptions to
10 CFR 830, Subpart B for
SC Hazard Category 1, 2, and 3 nuclear facilities. This
authority cannot be delegated.
-
Approval Authority for alternate safe harbor
methodologies for Hazard Category 1, 2, and 3 nuclear facilities following Office
of Health, Safety & Security (HSS) concurrence has been specifically delegated
in writing to the Deputy Director for Field Operations (DDFO) (SC-3) per January 26, 2012 memorandum from the SC Director. See current delegations at http://scms.sc.doe.gov/Reports/DelegationsList.cfm.
Startup Authorization Authority for:
-
Initial startup after conversion of an existing facility to a new Hazard Category 1 or 2 nuclear facility with a new DSA and TSRs when delegated.
-
Restart of facility, activity or operation that has upgraded its hazard categorization to hazard category 1 or 2, when delegated.
-
Restart of a Hazard Category 1 nuclear facility, activity, or operation following extended shutdown (>12 months).
-
Approval of Startup Notification Reports when SC-1 is the Startup Authorization Authority; otherwise make recommendation regarding approval.
-
Approval of Startup Notification Reports when SC-1 is the startup Authorization Authority; otherwise make recommendation regarding approval.
-
Reviews and approves exemptions to DOE O 425.1D for SC facilities.
For an accelerator facility (or module) that have the
potential for more than minor onsite or more than negligible
offsite impacts to workers, the public or the environment:
-
Appoints Review Team Leader for accelerator
safety documents.
-
Approves documentation of DOE reviews and bases
for approval and associated Accelerator Safety
Envelopes (ASEs), ASE revisions, and Unreviewed
Safety Issue (USI) change packages.
-
Approval Authority for commissioning, startup,
and restart of accelerator facilities and
modules and exemptions from the requirements
of DOE O 420.2C.
|
SC Deputy Director
for Field Operations (DDFO), Office of Science (SC‑3) |
The SC DDFO is the
Approval Authority for Hazard Category 1, 2, and 3 nuclear
facilities safety basis documentation per the delegation letter
from the SC Director to the Deputy Director for Field Operations
(DDFO) (SC-3) per January 26, 2012 memorandum. Some additional
delegations have been made to Site Office Managers beyond SC-3.
See current delegations at http://scms.sc.doe.gov/Reports/DelegationsList.cfm.
-
Ensures that all SC sites have approved
Documented
Safety Analyses (DSAs), Technical
Safety Requirements (TSRs) and Safety
Evaluation Reports (SERs) for its Hazard
Category 1, 2, or 3 nuclear facilities
and onsite transportation actives meeting
Hazard Category 2 and 3 nuclear facilities
criteria.
-
Appoints Review Team Leader for safety
basis documents and contractor’s
new or revised procedure for its USQ
process.
-
Approves SERs and associated DSAs, TSRs, Justification
for Continued Operations (JCOs), Unreviewed
Safety Question (USQ) change packages and
other safety documents for Hazard Category
1, 2, or 3 nuclear facilities and facilities
downgraded to below Hazard Category 3 Threshold
Quantities by analysis.
-
Approves SERs and associated Transportation
Safety Documents (TSDs), USQ change packages,
and other safety documents for onsite transportation
activities meeting Hazard Category 2 or 3
nuclear facilities criteria.
-
Approves SERs and contractor’s new
or revised procedure for its USQ process.
-
Approves requests for any changes to due dates
related to the review and approval of a safety
basis document for Hazard Category 1, 2, or
3 nuclear facilities that extends beyond the
established time frame.
-
Assists and oversees the Site Offices of Hazard
Category 1, 2, and 3 nuclear facilities implementation
of their safety basis responsibilities to
ensure compliant and effective programs.
For startup and restart of Hazard Category 1, 2, and
3 nuclear facilities serves as the Startup Authorization Authority for:
-
Newly constructed Hazard Category 3 nuclear facility with a new DSA and TSRs.
-
Initial startup of a newly constructed Hazard Category 1, 2 or 3 nuclear activity or operation with a new DSA and TSRs that is commensurate with the DSA approval authority.
-
Initial startup after conversion of an existing facility to a new Hazard Category 3 nuclear facility with a new DSA and TSRs.
-
Restart of facility, activity or operation that has upgraded its hazard categorization to hazard category 3.
-
Restart of a Hazard Category 2 nuclear facility, activity, or operation following extended shutdown (>12 months).
-
Restart following shutdown because of substantial process, system or facility modifications of a Hazard Category 1 or 2 nuclear facility, activity or operation. Restart of a Hazard Category 1 nuclear facility following shutdown due to a violation of a safety limit.
-
Approval of Startup Notification Reports when SC-3 is the Startup Authorization Authority; otherwise make recommendation regarding approval
For an accelerator facility (or module) that have the
potential for more than minor onsite or more than negligible
offsite impacts to workers, the public or the environment,
as delegated by the SC Director:
-
Appoints Review Team Leader for accelerator safety
documents.
-
Approves documentation of DOE reviews and bases
for approval and associated ASEs, ASE revisions,
and USI change packages.
-
Approval Authority for commissioning, startup,
and restart of accelerator facilities and
modules and exemptions from the requirements
of DOE O 420.2C.
Ensures
through staff the implementation of this subject
area and its procedures by the SC Site Offices. |
SC Site Office Managers |
Note that this list
is dependent upon if the Approval Authority has been delegated
-
When delegated Approval Authority by SC‑3,
approves SERs and associated DSAs, TSRs, JCOs,
USQ change packages, TSDs, USQ procedure and
other safety documents for nuclear facilities
safety basis. If the Approval
Authority is at Headquarters (HQ), transmits
the request for approval (including the
contractor safety basis document and
corresponding SER) to the HQ Approval
Authority.
-
Prepares SERs and makes recommendations to
the Approval Authority for associated DSAs,
TSRs, JCOs, TSDs, USQ change packages and
other safety documents for Hazard Category
1, 2, or 3 nuclear facilities, facilities
downgraded to below Hazard Category 3 Threshold
Quantities by analysis, and onsite transportation
actives meeting Hazard Category 2 and 3 nuclear
facilities criteria.
-
Prepares SERs and makes recommendations
to the Approval Authority for new or
revised contractor’s procedure
for its USQ process.
-
Prepares and provides input to the Safety
Basis Information System on a quarterly basis (March,
June, September, and December each year) SBIS specific to their nuclear facilities
(Reference DOE O 231.1B, Environment,
Safety and Health Reporting).
-
Ensures that contractors develop safety
basis documentation consistent with the
Approval Authority’s expectations.
-
Establishes a management process consistent
with regulatory and Departmental expectations
for the review and approval of safety basis
documents and that also addresses the following
requirements:
-
Timeframes for reviewing and approving
safety basis documents consistent with
the approval authority’s expectations;
-
Documentation of the review and basis for approval
in the SER;
-
Approval of SERs and their corresponding safety
basis documents, including transmittal of
recommendations for approval to the approval
authority if approval has not been delegated;
-
Transmittal of comments/issues and approvals
to the contractor, through the Contracting
Officer’s Representative;
-
Prompt identification, proper reporting, and
timely correction of safety basis document
implementation issues;
-
Maintenance of a list of Hazard Category 1,
2, and 3 nuclear facilities, facilities downgraded
to below Hazard Category 3 Threshold Quantities
by analysis, and onsite transportation actives
meeting Hazard Category 2 and 3 nuclear facilities
criteria and their corresponding safety basis
documents; and
-
Evaluation of contractor’s annual
summary report for USQ determinations
performed since its last submittal.
-
Maintains a sufficient number of qualified
staff to review safety basis documents
and prepares SERs in conjunction with
resources available from the Integrated
Support Centers and DOE‑HQs.
-
Provides guidance to contractors concerning
safety basis issues, when necessary.
-
Reviews submitted safety basis documents
and new or revised contractor’s
procedure for its USQ process for technical
accuracy and compliance with 10CFR830
and established DOE requirements, within
the established timeframes, and document
in the SER the results of the reviews.
-
Ensures contractor submits annually to DOE
a summary of USQ Determinations performed
since the prior submission and evaluates the
adequacy of the summaries.
-
When made aware of a Potential Inadequacy in Safety Analysis (PISA), monitors the
contractor’s
actions to place or maintain the facility
in a safe condition, appropriately notify
DOE, perform a USQ determination and
notify DOE promptly of the results, and
complete a EOS and submit it to DOE prior
to removing any operational restrictions;
evaluates actions to ensure they are
appropriate and directs additional actions
if necessary; reviews the USQ determination
and directs changes if warranted; and
reviews the EOS.
-
Resolves issues, comments and differing technical
opinions that cannot be satisfactorily resolved
by the reviewers.
-
Assesses contractor safety basis processes
and activities.
-
Reviews proposed exemption requests and
alternate safe harbor methods, and provides
recommendations and submits to the SC
Director.
-
Ensures safety documents, new and revised
contractor’s
procedure for its USQ process, SERs,
and associated review and approval documentation
are controlled and maintained as quality
assurance records.
For Radiological Facilities, the Site Office Manager is
the Approval Authority when the DOE Site Office has
withdrawn the contractor’s authorization to approve
its own radiological facility safety basis documents.
For startup and restart of Hazard Category 1, 2, and
3 nuclear facilities:
-
Determines and ensures the contractor determines if the appropriate type of readiness review is required for startup or restart of SC nuclear facilities using the requirements from DOE O 425.1D.
-
Serves as the Startup Authorization Authority for startups
and restarts for which ORRs/RAs are required if
a field official deemed an ORR/RA appropriate.
-
Reviews and approves each SNR from site’s
contractor(s). Provides comments and makes
a recommendation regarding approval of SNRs to
SC‑Headquarters when the Startup Authorization
Authority resides at Headquarters.
-
Forwards SNRs with Site Office comments and actions/approval to the SC-3, HSS, and the SC Central Technical Authority as appropriate.
-
For ORRs/RAs, requires the contractor to prepare
SNRs, plans of action, ORRs/RAs and final
reports. Prepares
as appropriate DOE plans of action, ensures ORR
team leaders prepare ORR Implementation Plans and
final reports. Ensures resolution of
all findings from the ORRs are documented
and maintained with plans of actions, implementation
plans and final reports.
-
For DOE ORRs/RAs, develops the breadth of the ORR/RA
and documents it in the Plan of Action.
-
For ORRs/RAs, ensures the contractor and DOE ORR/RA Plans of Action are approved by the appropriate Startup Authorization Authority. Ensures that the contractor’s Plan of Action specifies the prerequisites for starting the contractor’s ORR and prerequisites address each of the core requirements of DOE O 425.1D. Ensures the DOE Plan of Action specifies additional prerequisites. Ensures the DOE and contractor Plans of Action are provided for review and comment to HSS.
-
Ensures that contractor management appoints review team leaders in accordance with the qualifications and training requirements of DOE O 425.1D.
-
Ensures that ORR/RA teams do not include senior
members from offices assigned direct line management
responsibility for the work being reviewed unless
the startup authorization authority has approved an exemption.
-
Ensures that the contractor’s ORR team
determines the criteria and review approaches
to be used for their review based on the approved
breadth given in their Plan of Action.
-
Ensures that the review team (both DOE and contractor)
documents the criteria and review approaches in
their ORR Implementation Plans.
-
Ensures that the contractor’s ORR team
leader approves their implementation plan
to conduct the ORRs.
-
Requires the DOE and contractor POAs, implementation plans, readiness to proceed memoranda and final reports be provided to the HSS, the SC Central Technical Authority and SC-3 for review and comment.
-
Ensures all actions required for an ORR/RA startup
or restart are completed with the exception
of a manageable list of open pre‑start
findings.
-
Ensures that actions are documented that verify
Site Office and contractor readiness, including
review of closure of contractor ORR/RA findings,
assessments of completion of defined prerequisites
and other assessments performed to ascertain readiness.
-
Ensures the DOE ORR/RA team leader prepares and
approves a final report that documents the results
of the ORR/RA and makes a conclusion as to whether
startup or restart of the nuclear facility can
proceed safely.
-
Ensures the mechanism for closure of DOE ORR
findings includes the following: (1) development
of plans of actions approved by DOE to correct
the findings. Action
plans must provide evaluation of any overall programmatic
deficiencies and root causes; (2) documentation
of completion of response actions responding to
the findings in a closure package. Closure
packages must include a brief description of actual
corrective actions taken and reasons for concluding
that closure has been achieved; (3) DOE verification
of closure of pre‑start findings.
-
Ensures the contractor has satisfactorily resolved
all pre‑start findings of the DOE ORR
prior to the startup or restart of the nuclear
facility.
-
Establishes procedures for readiness reviews consistent with DOE O 425.1D.
-
Ensures
contractors procedures gain Site Office concurrence prior to implementation of the order These procedures must require submittal of a startup notification report to obtain approval to use an RA/ORR and preparation of a formal Plan of Action that includes, as a minimum, the breadth of the assessment, team leader designation, and prerequisites for the assessment. Ensures the SNR and Plan of Action are approved by the Startup Authorization
Authority.
-
Ensures that the core requirements consistent
with DOE O 425.1D, are applied when developing an ORR and an RA.
-
Ensures that the core requirements applicable to
Site Office personnel have been evaluated and documented
in the DOE Plan of Action.
-
Ensures that Site Office and contractor procedures
are consistent with DOE O 425.1D.
-
Maintains a sufficient number of qualified staff
to provide readiness activities expertise to the
Site Office.
For facilities which have Authorization Agreements:
-
Determines which facilities should have authorization
agreements.
-
Maintains authorization agreements with the contractor
responsible for facilities that are designated
to have authorization agreements.
-
Initiates update of authorization agreements with
the contractor as necessary.
-
Ensures implementation of authorization agreements
are verified annually.
-
Ensures violations of authorization agreements are
properly reported.
-
Ensure authorization agreement records are properly
retained as Quality Assurance records.
For accelerator facilities and modules:
-
Ensures the contractor appropriately applies the
graded approach in the development of accelerator
safety documents; establishes the requirement that
any activity violating the ASE must be terminated
immediately and the Site Office notify; establishes
and implements an effective internal review and
approval process for accelerator safety documentation;
and keeps the Site Office aware of Safety Assessment
Document (SAD) preparation status and proposed
changes.
-
Ensures the contractor has properly implemented
the accelerator safety documentation.
-
Ensures accelerator safety documents, documentation
of DOE reviews and bases for approval, and associated
review and approval documentation are controlled
and maintained as quality assurance records.
For an accelerator facility (or module) that have the
potential for more than minor onsite or more than negligible
offsite impacts to workers, the public or the environment,
reviews ASEs, ASE revisions, USI change packages and
accompanying SADs; prepares documentation of DOE reviews
and bases for approval, and obtains approval of the
ASEs, ASE revisions, USI change packages, and documentation
of DOE reviews and bases for approval from the Approval
Authority.
For an accelerator facility (or module) that do not have
the potential for more than minor onsite or more than
negligible offsite impacts to workers, the public or
the environment, reviews ASEs, ASE revisions, USI change
packages and accompanying SADs; prepares documentation
of DOE reviews and bases for approval, and approves
the ASEs, ASE revisions, USI change packages, and documentation
of DOE reviews and bases for approval.
For small non‑complex accelerator facilities and modules
with the potential for only local work area impacts
(DOE G 420.2‑1, Table 1), ensures the contractor
appropriately implements the applicable standards and
guides.
For startup and operation of accelerator facilities
and modules:
-
Approves the start of commissioning for an accelerator
facility (or module) that does not have potential
for more than minor onsite or more than negligible
offsite impacts to workers, the public or the environment
after evaluating the ASE, accelerator readiness
review (ARR), and SAD and determining that a specific
ASE will appropriately bound commissioning; that
an appropriate ARR was conducted; and that the
risks as analyze in the SAD are acceptable when
commissioning is conducted within the specified
ASE.
-
Approves start of routine operation for an accelerator
facility (or module) that does not have potential
for more than minor onsite or more than negligible
offsite impacts to workers, the public, or the
environment after evaluating the ASE, ARR and SAD
and determining that the ASE will appropriately
bound routine operation; that an appropriate ARR
was conducted; and that the risks as analyzed in
the SAD are acceptable when routine operations
are conducted within the specified ASE.
-
After ensuring that an appropriate ARR was conducted
and that the risks as analyzed in the SAD are acceptable
when commissioning is conducted within the specified
ASE, recommends to the SC Director approval for
start of commissioning activities for an accelerator
facility (or module) that has the potential for
more than minor onsite or more than negligible
offsite impacts to workers, the public, or the
environment.
-
After ensuring that an appropriate ARR was conducted
and that the risks as analyzed in the SAD are acceptable
when routine operations are conducted within the
specified ASE, recommends to the SC Director approval
for start of routine operations for an accelerator
facility (or module) that has the potential for
more than minor onsite or more than negligible
offsite impacts to workers, the public, or the
environment.
-
Approves restart of an activity at an accelerator
facility after shutdown that was ordered by a Site
Office Manager because of an USI, ASE violation,
or other safety concern.
-
Approves exemptions from requirements of DOE O 420.2C
for an accelerator facility or module that does
not have the potential for more than minor onsite
or more than negligible offsite impacts to workers,
the public or the environment.
-
Ensures that the Contractor Requirements Document
of DOE O 420.2C or alternative standard (consistent
with the terms of the laws, regulations, and DOE
directive clause of the contract) is incorporated
into the contract of each affected site/facility
management contractor through the cognizant contracting
officer.
-
Implements the site office responsibilities of this
procedure.
|