USEC Inc. American Centrifuge Plant Application Review Schedule
NRC staff has developed the following license review schedule.
C = Completed
Date | Action |
---|---|
10/7/04 C | (NMSS) Issue acceptance/rejection letter |
1/05 C | (NMSS) Conduct EIS scoping meeting |
2/05 C | (NMSS) Complete safety and security reviews and issue RAIs |
2/05 C | (NMSS) Complete environmental review and issue RAIs |
3/05 C | (NMSS) Receive USEC Inc. responses to safety and security RAIs |
8/05 C | (NMSS) Receive USEC Inc. responses to environmental RAIs |
4/05 C | (NMSS) Issue EIS scoping summary report |
9/05 C | (NMSS) Issue draft EIS for public comment |
9/05 C | (NMSS) Conduct draft EIS public meeting |
5/06 C | (NMSS) Publish final EIS |
9/06 C | (NMSS) Publish final SER |
3/07 C | (NMSS) Begin ASLB oral hearings |
4/07 C | (NMSS) ASLB decision |