Application Information:
License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 06/22/11 | 06/22/11 |
Publish Federal Register Notice (FRN) – LRA availability | 07/2011 | 07/26/11 |
Publish FRN – acceptance/rejection and opportunity for hearing | 08/2011 | 08/24/11 |
Publish FRN – environmental scoping meeting | 08/2011 | 08/26/11 |
Public Meeting – License Renewal Overview and Environmental Scoping meeting | 09/22/11 | 09/22/11 |
Audit – Scoping & Screening Methodology | 09/19-23/11 | 09/19-23/11 |
Deadline for filing hearing requests and petitions for intervention | 10/24/11 | 10/24/11* |
Environmental scoping period ends | 10/28/11 | 10/28/11 |
Audit – Aging Management Programs | 10/03-14/11 | 10/03-14/11 |
Audit – Environmental | 11/07-10/11 | 11/07-10/11 |
Inspection – Regional | 06/04-08/12 06/18-22/12 |
06/04-08/12 06/18-22/12 |
Issue safety evaluation report (SER) with open items | 07/2012 | 07/31/12 |
Issue draft supplemental environmental impact statement (SEIS) | TBD | |
Publish FRN – draft SEIS available for comments | TBD | |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | 09/2012 | |
Public Meeting – draft SEIS meeting | TBD | |
End of draft SEIS comment period | TBD | |
Issue final SER | 01/2013 | |
ACRS full committee meeting | 02/2013 | |
Issue final SEIS | TBD | |
U.S. Environmental Protection Agency FRN Published – availability of final SEIS | TBD | |
Decision – Director, NRR (22 months if no hearing) | TBD |
*Extended to 11/22/2011 for the Natural Resources Defense Council per Order of the Secretary of the Commission.
Note: The Limerick Generating Station review schedule was revised as described in the letter below:Safety Evaluation Report
The NRC staff reviewed the Limerick Generating Station, Units 1 and 2, license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on July 31, 2012, as "Safety Evaluation Report with Open Items Related to the License Renewal of Limerick Generating Station, Units 1 and 2."
Project Managers for Limerick
Limerick Generating Station, Units 1 and 2 PMs | |
---|---|
License Renewal (Safety) | Robert Kuntz |
License Renewal (Environmental) | Leslie Perkins |
Lead Power Plant | Rick Ennis |