Callaway Plant, Unit 1 – License Renewal Application
On this page:
Application Information:
- License Renewal Application
- Applicant's Environmental Report
- Cover through Chapter 2 – 16.1 MB
- Chapter 3 through Attachment D – 21.5 MB
- Attachment E through End – 7.0 MB
- Full Environmental Report – 43.7 MB
- Full Environmental Report, reduced file size – 10.8 MB
License Renewal Review Schedule*:
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 12/19/11 | 12/19/11 |
Publish Federal Register Notice (FRN) – LRA availability | 01/2012 | 01/03/12 |
Publish FRN – acceptance/rejection and opportunity for hearing | 02/2012 | 02/24/12 |
Publish FRN – environmental scoping meeting | 02/2012 | 02/24/12 |
Public Meeting – License Renewal Overview and Environmental Scoping meeting | 03/14/12 | 03/14/12 |
Deadline for filing hearing requests and petitions for intervention | 04/24/12 | 04/24/12 |
Environmental scoping period ends | 04/24/12 | 04/24/12 |
Audit – Scoping & Screening Audit Methodology | 04/16/12 | 04/16/12 |
Audit – Aging Management Programs | 04/30/12 | 04/30/12 |
Audit – Environmental | 05/22/12 | 05/22/12 |
Issue draft supplemental environmental impact statement (SEIS) | 02/2013 | |
Publish FRN – draft SEIS available for comments | 02/2013 | |
Public Meeting – draft SEIS meeting | 03/2013 | |
Issue safety evaluation report (SER) with open items | 04/2013 | |
End of draft SEIS comment period | 04/2013 | |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | 05/2013 | |
Issue final SER | 09/2013 | |
Issue final SEIS | 09/2013 | |
U.S. Environmental Protection Agency FRN Published – availability of final SEIS | 09/2013 | |
ACRS full committee meeting | 10/2013 | |
Decision – Director, Office of Nuclear Reactor Regulation (22 months if no hearing) | 12/2013 | |
Commission decision (30 months if hearing) | TBD |
Project Managers for Callaway Plant
Callaway Plant, Unit 1 PMs | |
---|---|
License Renewal (Safety) | Samuel Cuadrado de Jesús |
License Renewal (Environmental) | Carmen Fells |
Lead Power Plant | Andrew Hon |
Page Last Reviewed/Updated Wednesday, August 22, 2012