Callaway Plant, Unit 1 – License Renewal Application

Photograph of Callaway

On this page:

Application Information:

To top of page

License Renewal Review Schedule*:

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 12/19/11 12/19/11
Publish Federal Register Notice (FRN) – LRA availability 01/2012 01/03/12
Publish FRN – acceptance/rejection and opportunity for hearing 02/2012 02/24/12
Publish FRN – environmental scoping meeting 02/2012 02/24/12
Public Meeting – License Renewal Overview and Environmental Scoping meeting 03/14/12 03/14/12 
Deadline for filing hearing requests and petitions for intervention 04/24/12 04/24/12
Environmental scoping period ends 04/24/12  04/24/12
Audit – Scoping & Screening Audit Methodology 04/16/12 04/16/12
Audit – Aging Management Programs 04/30/12 04/30/12
Audit – Environmental 05/22/12 05/22/12
Issue draft supplemental environmental impact statement (SEIS) 02/2013  
Publish FRN – draft SEIS available for comments 02/2013  
Public Meeting – draft SEIS meeting 03/2013  
Issue safety evaluation report (SER) with open items 04/2013  
End of draft SEIS comment period 04/2013  
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 05/2013  
Issue final SER 09/2013  
Issue final SEIS 09/2013  
U.S. Environmental Protection Agency FRN Published – availability of final SEIS 09/2013  
ACRS full committee meeting 10/2013  
Decision – Director, Office of Nuclear Reactor Regulation (22 months if no hearing) 12/2013  
Commission decision (30 months if hearing) TBD  

To top of page

Project Managers for Callaway Plant

Callaway Plant, Unit 1 PMs
License Renewal (Safety) Samuel Cuadrado de Jesús
License Renewal (Environmental) Carmen Fells
Lead Power Plant Andrew Hon