Seabrook Station, Unit 1 - License Renewal Application

Photograph of Seabrook 1

On this page:

Application Information:

To top of page

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 06/01/10 06/01/10
Publish Federal Register Notice (FRN) – LRA availability 06/14/10 06/16/10
Publish FRN – acceptance/rejection and opportunity for hearing 07/23/10 07/21/10
Publish FRN – environmental scoping meeting 07/23/10 07/20/10
Public Meeting – License Renewal Overview and Environmental Scoping meeting 08/19/10 08/19/10
Audit – Scoping & Screening Audit Methodology 09/20/10 09/20/10
Deadline for filing hearing requests and petitions for intervention 09/20/10* 10/20/10
Environmental scoping period ends 09/21/10 09/21/10
Audit – Environmental 10/04/10 10/05/10
Audit – Aging Management Programs 10/12/10 10/12/10
Issue draft supplemental environmental impact statement (SEIS) 08/2011 08/01/11
Publish FRN – draft SEIS available for comments 08/2011 08/12/11
Public Meeting – draft SEIS meeting 08/2011 09/15/11
End of draft SEIS comment period 11/2011 10/26/11
Issue safety evaluation report (SER) with open items 06/2012 06/08/12
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 07/2012  
Issue draft supplement to the Seabrook draft SEIS 04/2013  
Publish FRN – draft supplement to the Seabrook draft SEIS available for comments. 04/2013  
Issue final SER TBD  
ACRS full committee meeting TBD  
End of comment period on the draft supplement to the Seabrook draft SEIS TBD  
Issue final SEIS TBD  
Decision – Director, Office of Nuclear Reactor Regulation TBD  
Commission decision TBD  

* Extended to 10/20/10 for the State of New Hampshire, Beyond Nuclear, Friends of the Coast, the New England Coalition, the Seacoast Anti-Pollution League, and the New Hampshire Sierra Club per Order of the Secretary of the Commission.

Note: The Seabrook Station review schedule was revised as described in the letters below:

To top of page

Safety Evaluation Report

The NRC staff reviewed the Seabrook Station license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on June 8, 2012, as "Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station."

To top of page

Environmental Impact Statement

NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Seabrook Station (NUREG-1437, Supplement 46) Draft Report for Comment,” was published in July 2011. This supplement documents the NRC staff’s review of the environmental issues at Seabrook Station regarding the NextEra Energy Seabrook, LLC application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff’s analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC staff’s preliminary recommendation regarding the proposed action.

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
09/15/11

Meeting to discuss the preliminary results of the environmental review for Seabrook Station.

08/19/10

Meeting to discuss the license renewal process and environmental scoping for Seabrook Station.

To top of page

Project Managers for Seabrook Station, Unit 1

Seabrook Station, Unit 1 PMs
License Renewal (Safety) Pat Milano
License Renewal (Environmental) Lois James
Lead Power Plant John Lamb