General Information

Top of Page

NEXT Project

NEXT stands for NSLS-II Experimental Tools, a set of five or six beamlines being developed for the National Synchrotron Light Source II (NSLS-II), with funding from the U.S. Department of Energy (DOE).
  • Mission Need
  • CDR
  • PDR
  • IPT
  • Project Organization
  • Beamline Advisory Teams (BATs)
  • CD-0 May 27, 2010 (actual)
  • CD-1 Dec 19, 2011 (actual)
  • CD-2 August 2013 (planned review)
  • CD-3 Dec 2013 (planned)
  • CD-4 Sep 2017 (planned)

DOE CD-2 Review July 30-August1, 2013 (scheduled)
ALD’s PDR Review Mar 6-7, 2013 (scheduled)
DOE Status Review, Sep 11-13, 2012
ALD’s Status Review, Aug 7-9, 2012
DOE CD-1 Review, Aug 31-Sep 1, 2011
ALD’s CDR Review, Jun 28-29, 2011

 

2013
2012
2011