USDOT Federal Highway Administration USDOT Home | FHWA Home | Feedback
Skip to main content

Project Profiles

LA 1 Improvements

Location

Leeville, Louisiana

Project Sponsor / Borrower

Louisiana Department of Transportation and Development (LADOTD)

Louisiana Transportation Authority (LTA)

Program Areas

Project FinanceTIFIARevenue - Road Pricing Revenue

Fiscal Year Approved

Fiscal Year 2005

Mode

Toll Highway

Description

The LA 1 Improvements project will provide an 18-mile, fully access controlled, elevated toll highway on a new location between Golden Meadow (LA 3235) and Port Fourchon (LA 3090). The existing LA 1 requires replacement because of subsidence, erosion, and frequent storm damage. In the event of hurricanes, it is the only highway evacuation route for Port Fourchon and Grande Isle, both of which suffered extensive damage from Hurricanes Katrina and Rita in 2005.

The project is being constructed in phases:

  • Phase 1A: Fourchon to Leeville Bridge - Approximately 7 miles, 40-foot wide, two-lane elevated highway south of Leeville Bridge to LA 3090 in Port Fourchon. (Open to traffic)
  • Phase 1B: Leeville Bridge Approaches and Connector - Two-lane interchanges and connector roads north and south of the Leeville Bridge. (Open to traffic)
  • Phase 1C: Leeville Bridge Replacement - Two-lane, fixed-span, high-level bridge (Tomey J. Doucet Bridge) over Bayou Lafourche. (Open to traffic)
  • Phase 1D: Customer service center, kiosk network, open-road tolling equipment and intelligent transportation systems (ITS). (Completed)
  • Phase 2: 8.3-mile, two-lane, elevated highway from Leeville to Golden Meadow (LA 3235). (Permitting completed, segmented design underway)

Cost

Phase 1: $371.6 million

Phase 2: $320 million

Funding Sources

Total Phase 1 cost is $371.6 million :

  • Senior revenue bonds - $70.4 million
  • TIFIA Loan - $66 million
  • Federal Formula Funds - $42.6 million
  • Federal Earmarks - $81.6 million
  • State TTF - $12.9 million
  • State GO Bonds - $60 thousand
  • State General Fund Surplus - $63 million
  • CIAP Funds - $35 million

Project Delivery / Contract Method

Phase 1: One design contract and four design-bid-build-construction contracts.

Private Partner

None

Project Advisors / Consultants

Wilbur Smith Associates - Traffic & Revenue

URS

To USDOT TIFIA JPO:

  • TIFIA Financial Advisor: Scully Capital Services, Inc
  • TIFIA Legal Advisor: Ballard Spahr

Lenders

Bondholders, USDOT TIFIA

Duration / Status

Phase 1 construction began March 2006 and was completed December 2011.

Phase 2 under design.

TIFIA Credit Assistance

Direct Loan: $66 million

All project debt will be repaid from toll revenues. The financial plan shows TIFIA principal and interest payments beginning in 2013 with final payment in 2040.

Financial Status / Financial Performance

TIFIA credit agreement signed May 2005

Along with the $95 million in senior revenue bonds issued at the time of the closing of the TIFIA loan, LTA issued $66 million of low interest Bond Anticipation Notes (BANs) that matured in 2009. When the BANs became due, LTA drew down the TIFIA Loan to repay the BANs. The total amount of the TIFIA Loan, $66 million, was drawn in August, 2009.

Innovations

The project is designed so that major portions can be constructed using "end-on-end" construction methods to protect sensitive wetlands and marshes. A movable truss and crane system obviates the need for conventional temporary haul roads and construction pads.

Related Links / Articles

Project Website

LA 1 Coalition

GeauxPass Toll Information

TOLLROADSnews Article (Aug. 17, 2009)

Contacts

William Huffstetler
CDM Smith
huffstetlerw@cdmsmith.com