Preliminary Design Review (PDR)

Definition

A multi-disciplined technical review to ensure that a system is ready to proceed into detailed design and can meet stated performance requirements within cost (program budget), schedule (program schedule), risk, and other system constraints.

General/Information/Narrative

Generally, this review assesses the system preliminary design as captured in performance specifications for each configuration item in the system (allocated baseline), and ensures that each function in the functional baseline has been allocated to one or more system configuration items. Normally conducted during the Technology Development phase (TD) phase, but may also be conducted early in the Engineering and Manufacturing Development (EMD) phase. (DoDI 5000.02) See Functional Baseline and Allocated Baseline.

The PDR is a technical assessment establishing the physically allocated baseline to ensure that the system under review has a reasonable expectation of being judged operationally effective and suitable. This review assesses the allocated design documented in subsystem product specifications for each configuration item in the system and ensures that each function, in the functional baseline, has been allocated to one or more system configuration items. The PDR establishes the allocated baseline (hardware, software, human/support systems) and underlying architectures to ensure that the system under review has a reasonable expectation of satisfying the requirements within the currently allocated budget and schedule.

The implementation of the Weapon Systems Acquisition Reform Act of 2009 (see Directive-Type Memorandum (DTM) 09-027 – Implementation of the Weapon Systems Acquisition Reform Act of 2009) directs the following:

a.)      PDRs before MS B are mandatory for all Major Defense Acquisition Programs (MDAPs) and will be reflected in the Technology Development Strategy (TDS) to be approved by the Milestone Decision Authority at Milestone A. Post-PDR assessments will be conducted in association with MS B preparations and will be formally considered by the Milestone Decision Authority at the Milestone B certification review.

b.)     The timing of PDRs for other than MDAPs will be approved by the DoD Component MDA when consistent with TDS or Acquisition Strategy objectives. When the PDR is conducted before MS B, a post-PDR assessment will be conducted in association with the MS B review and formally considered by the MDA at the MS B review. If the PDR is conducted after MS B, the MDA will conduct a post-PDR assessment at a time reflected in the approved acquisition strategy.

c.)      PDR before MS B is now a statutory requirement for MDAPs. The post-PDR assessment will be conducted during the MS B review, and prior to the section 2366b certification by the MDA per title 10, Unites States Code.

The PDR is conducted after preliminary design efforts, but before start of detail design. This review is the first opportunity for the Government to closely observe the Contractor's hardware and software design. The Contractor is expected to describe all design changes made with respect to the original design disclosed in the technical proposal and to provide rationale for the changes. The contractor may also provide a hardware or hands-on demonstration of some of the preliminary designs to better illustrate important aspects.

Policies, Directives, Regulations, Laws

Weapon Systems Acquisition Reform Act of 2009

United States Code Title 10 § 2366b

DoDI 5000.02, Operation of the Defense Acquisition System

Best Practices, Lessons Learned, Stories, Guides, Handbooks, Templates, Example Tools, Communities of Practice, LEC Tools

Defense Acquisition Guidebook: https://acc.dau.mil/adl/en-US/350719/file/49150/dag_08-05-10pdf

PowerLOG supports this activity by tracking the parts breakdown of a system using LCNs (LSAR Control Number), PLISNs (Provisioning List Item Sequence Number), and NHAs (Next Higher Assembly).  The Bill of Materials (LSA-080 BOM) and Provisioning Parts Breakout (LSA-154) provide reports related to the baseline configuration in this phase of the acquisition life cycle.  PowerLOG is a logistics data management system developed to support the development, integration, and review of logistic product information throughout the acquisition life cycle.  PowerLOG implements the Logistics Support Analysis Record (LSAR) requirements defined in MIL-STD-1388-2B as well as Logistics Product Data (LPD) standards defined by GEIA-STD-0007.  PowerLOG also supports legacy data standards such as MIL-STD-1552 (PMR).   PowerLOG is available free to all Government agencies and their contractors and can be obtained by visiting:  https://www.logsa.army.mil/lec/powerlog/.

The Cost Analysis Strategy Assessment (CASA) Life-Cycle Cost Estimating Software uses an engineering cost model to estimate total cost of ownership based on RDT&E, Acquisition/Procurement, O&S, and Disposal activities. In addition to life-cycle cost estimation, CASA can perform trade-offs, production rate, warranty effectiveness, and other economic analyses. CASA is distributed freely to all US personnel. Request from foreign nations for CASA and associated training and technical support are handled through a Foreign Military Sales Case (FMS). CASA can be obtained here:  https://www.logsa.army.mil/lec/casa/.

Training Resources

Related Articles

Required for:

Responsible Activity:

Definition General Info Policies Guides Communities Training Related


List of All Contributions at This Location

No items found.

Popular Tags

Page Information

At this page:
6644 Page Views 0 Pages Emailed
0 Meta-card Views 0 Documents and Videos
0 Questions 0 Attachments Downloaded
0 Answers 0 Videos downloaded
0 Relationships and Highlights
ID247072
Date CreatedTuesday, November 18, 2008 11:24 AM
Date ModifiedWednesday, January 11, 2012 10:23 AM
Version Comment:

Sign In

Login with your CAC

Insert your CAC now, and click this button.


Login with your Password

User Name:

Password:

Forgot your password?

  

Benefits of ACC Membership


Browse

https://acc.dau.mil/UI/img/bo/minus.gifIntegrated Logistic Support and Logistic...
https://acc.dau.mil/UI/img/bo/plus.gif Materiel Development Decision ...
https://acc.dau.mil/UI/img/bo/plus.gifAcquisition Decision Memorandum
https://acc.dau.mil/UI/img/bo/plus.gifAcquisition Decision Memorandum - Phase...
https://acc.dau.mil/UI/img/bo/plus.gifAcquisition Program Baseline
https://acc.dau.mil/UI/img/bo/plus.gifAcquisition Strategy
https://acc.dau.mil/UI/img/bo/plus.gifAffordability Assessment
https://acc.dau.mil/UI/img/bo/plus.gifAffordability Assessment - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifAllocated Baseline
https://acc.dau.mil/UI/img/bo/plus.gifAnalysis of Alternatives (AoA) - Phase 1
https://acc.dau.mil/UI/img/bo/plus.gifAnalysis of Alternatives (AoA) - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifApprove & Develop Test Equipment and...
https://acc.dau.mil/UI/img/bo/plus.gifAssess Support Needs
https://acc.dau.mil/UI/img/bo/plus.gifAssign ILS Manager
https://acc.dau.mil/UI/img/bo/plus.gifAssign Product Support Integrator
https://acc.dau.mil/UI/img/bo/plus.gifAssign TRADOC Capabilities Manager (TSM)
https://acc.dau.mil/UI/img/bo/plus.gifBasis of Issue Plan
https://acc.dau.mil/UI/img/bo/plus.gifBasis of Issue Plan Feeder Data
https://acc.dau.mil/UI/img/bo/plus.gifCapability Development Document
https://acc.dau.mil/UI/img/bo/plus.gifCapability Production Document
https://acc.dau.mil/UI/img/bo/plus.gifComparative Analysis 1
https://acc.dau.mil/UI/img/bo/plus.gifComparative Analysis 2
https://acc.dau.mil/UI/img/bo/plus.gifComputer Resources Concept
https://acc.dau.mil/UI/img/bo/plus.gifComputer Resources Life Cycle Management...
https://acc.dau.mil/UI/img/bo/plus.gifComputer Resources Support
https://acc.dau.mil/UI/img/bo/plus.gifContinuous Technology
https://acc.dau.mil/UI/img/bo/plus.gifCore Depot Assessment
https://acc.dau.mil/UI/img/bo/plus.gifCore Logistics Analysis
https://acc.dau.mil/UI/img/bo/plus.gifCost Analysis
https://acc.dau.mil/UI/img/bo/plus.gifCost As Independent Variable - Phase 2
https://acc.dau.mil/UI/img/bo/plus.gifCost As Independent Variable - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifCritical Design Review
https://acc.dau.mil/UI/img/bo/plus.gifDA Authenticated Equipment Publications
https://acc.dau.mil/UI/img/bo/plus.gifDemilitarization Disposal Operations...
https://acc.dau.mil/UI/img/bo/plus.gifDemilitarization/Disposal
https://acc.dau.mil/UI/img/bo/plus.gifDepot Maintenance Weapon System Support...
https://acc.dau.mil/UI/img/bo/plus.gifDepot Maintenance Capability
https://acc.dau.mil/UI/img/bo/plus.gifDepot Maintenance Support Plan
https://acc.dau.mil/UI/img/bo/plus.gifDepot Test Equipment
https://acc.dau.mil/UI/img/bo/plus.gifDesign Influence
https://acc.dau.mil/UI/img/bo/plus.gifDesign Product Support Package
https://acc.dau.mil/UI/img/bo/plus.gifDesign Tradeoffs / ILS Tradeoffs ...
https://acc.dau.mil/UI/img/bo/plus.gifDevelop and Test Product Support Package
https://acc.dau.mil/UI/img/bo/plus.gifDevelop Modified Table of Organization &...
https://acc.dau.mil/UI/img/bo/plus.gifDiagnostics and Prognostics...
https://acc.dau.mil/UI/img/bo/plus.gifDisposal Implementation
https://acc.dau.mil/UI/img/bo/plus.gifDisposal Plan
https://acc.dau.mil/UI/img/bo/plus.gifDMSMS Plan
https://acc.dau.mil/UI/img/bo/plus.gifDraft Depot Maintenance Work...
https://acc.dau.mil/UI/img/bo/plus.gifDraft Maintenance Allocation Chart (MAC)...
https://acc.dau.mil/UI/img/bo/plus.gifEarly Fielding Analysis
https://acc.dau.mil/UI/img/bo/plus.gifEngineering and Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gifEngineering Change Proposals
https://acc.dau.mil/UI/img/bo/plus.gifEngineering for Transportability
https://acc.dau.mil/UI/img/bo/plus.gifEquipment Distribution Plan
https://acc.dau.mil/UI/img/bo/plus.gifEquipment Publications Concept
https://acc.dau.mil/UI/img/bo/plus.gifEquipment Publications Input to...
https://acc.dau.mil/UI/img/bo/plus.gifEstablish ILS Management Program
https://acc.dau.mil/UI/img/bo/plus.gifEstablish Integrated Concept Team
https://acc.dau.mil/UI/img/bo/plus.gifEstablish Maintenance Concept
https://acc.dau.mil/UI/img/bo/plus.gifEstablish Sustainment Requirements and...
https://acc.dau.mil/UI/img/bo/plus.gifExit Documents and Products
https://acc.dau.mil/UI/img/bo/plus.gifFacilities
https://acc.dau.mil/UI/img/bo/plus.gifFailure Modes Effects and Criticality...
https://acc.dau.mil/UI/img/bo/plus.gifFailure Modes Effects and Criticality...
https://acc.dau.mil/UI/img/bo/plus.gifFault Tree Analysis
https://acc.dau.mil/UI/img/bo/plus.gifField Data Through STAMIS
https://acc.dau.mil/UI/img/bo/plus.gifFinal MAC
https://acc.dau.mil/UI/img/bo/plus.gifFinal Reproducible Copy
https://acc.dau.mil/UI/img/bo/plus.gifFull Rate Production
https://acc.dau.mil/UI/img/bo/plus.gifFunctional Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gifFunctional Requirements - Phase 2
https://acc.dau.mil/UI/img/bo/plus.gifFunctional Requirements - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifGovernment-Furnished Equipment (GFE) ...
https://acc.dau.mil/UI/img/bo/plus.gifHandling and Storage Capability
https://acc.dau.mil/UI/img/bo/plus.gifHandling Equipment Considerations
https://acc.dau.mil/UI/img/bo/plus.gifHazardous Material Handling Requirements...
https://acc.dau.mil/UI/img/bo/plus.gifILS Program Metrics
https://acc.dau.mil/UI/img/bo/plus.gifImplement and Deploy Sustainment...
https://acc.dau.mil/UI/img/bo/plus.gifIndependent Logistics Assessment
https://acc.dau.mil/UI/img/bo/plus.gifInitial Business Case Analysis
https://acc.dau.mil/UI/img/bo/plus.gifInitial Capabilities Document
https://acc.dau.mil/UI/img/bo/plus.gifInitial Configuration Management Plan
https://acc.dau.mil/UI/img/bo/plus.gifInitial Functional Requirements Analysis...
https://acc.dau.mil/UI/img/bo/plus.gifInitial Maintenance Plan
https://acc.dau.mil/UI/img/bo/plus.gifInitial Operational Capability (IOC)
https://acc.dau.mil/UI/img/bo/plus.gifInitial Supportability Strategy
https://acc.dau.mil/UI/img/bo/plus.gifInitial System Engineering Plan
https://acc.dau.mil/UI/img/bo/plus.gifInitial Technical Review
https://acc.dau.mil/UI/img/bo/plus.gifInitiate Logistics Management...
https://acc.dau.mil/UI/img/bo/plus.gifInitiate PBL Activities
https://acc.dau.mil/UI/img/bo/plus.gifInitiate Supportability Analysis
https://acc.dau.mil/UI/img/bo/plus.gifIntegrated Baseline Review
https://acc.dau.mil/UI/img/bo/plus.gifIntegrated Logistics Support (ILS) ...
https://acc.dau.mil/UI/img/bo/plus.gifIntegrated Logistics Support Manager
https://acc.dau.mil/UI/img/bo/plus.gifItem Unique Identification Plan
https://acc.dau.mil/UI/img/bo/plus.gifLevel of Repair Analysis - Phase 2
https://acc.dau.mil/UI/img/bo/plus.gifLevel of Repair Analysis - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifLife Cycle Cost Analysis
https://acc.dau.mil/UI/img/bo/plus.gifLogistics Demonstration -
https://acc.dau.mil/UI/img/bo/plus.gifLogistics Demonstration Report
https://acc.dau.mil/UI/img/bo/plus.gifLogistics Inputs to Capabilities...
https://acc.dau.mil/UI/img/bo/plus.gifLogistics Inputs to TEMP
https://acc.dau.mil/UI/img/bo/plus.gifLogistics Support Considerations
https://acc.dau.mil/UI/img/bo/plus.gifLow Rate Initial Production (LRIP)
https://acc.dau.mil/UI/img/bo/plus.gifMaintain Equipment Publications/Update...
https://acc.dau.mil/UI/img/bo/plus.gifMaintenance Labor Requirements
https://acc.dau.mil/UI/img/bo/plus.gifMaintenance Operations
https://acc.dau.mil/UI/img/bo/plus.gifMaintenance Planning
https://acc.dau.mil/UI/img/bo/plus.gifManpower and Personnel Integration
https://acc.dau.mil/UI/img/bo/plus.gifManpower Requirements Criteria
https://acc.dau.mil/UI/img/bo/plus.gifMANPRINT Validation
https://acc.dau.mil/UI/img/bo/plus.gifMarket Research & Investigation - Phase...
https://acc.dau.mil/UI/img/bo/plus.gifMarket Research & Investigation - Phase...
https://acc.dau.mil/UI/img/bo/plus.gifMaterial Fielding Team Report
https://acc.dau.mil/UI/img/bo/plus.gifMaterial Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gifMaterial Transfer Plan
https://acc.dau.mil/UI/img/bo/plus.gifMateriel Condition Status Report
https://acc.dau.mil/UI/img/bo/plus.gifMateriel Fielding Plan -
https://acc.dau.mil/UI/img/bo/plus.gifMateriel Release -
https://acc.dau.mil/UI/img/bo/plus.gifMateriel Release Approval
https://acc.dau.mil/UI/img/bo/plus.gifMateriel Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gifMilestone A
https://acc.dau.mil/UI/img/bo/plus.gifMilestone B
https://acc.dau.mil/UI/img/bo/plus.gifMilestone C
https://acc.dau.mil/UI/img/bo/plus.gifMission Support Plan
https://acc.dau.mil/UI/img/bo/plus.gifModernization Through Spares
https://acc.dau.mil/UI/img/bo/plus.gifModernization Through Spares
https://acc.dau.mil/UI/img/bo/plus.gifModification Work Orders
https://acc.dau.mil/UI/img/bo/plus.gifModification Work Orders
https://acc.dau.mil/UI/img/bo/plus.gifMonitor PBL Metrics
https://acc.dau.mil/UI/img/bo/plus.gifNew Equipment Training
https://acc.dau.mil/UI/img/bo/plus.gifNew Equipment Training Plan
https://acc.dau.mil/UI/img/bo/plus.gifNew/Revised Equipment Publications
https://acc.dau.mil/UI/img/bo/plus.gifOperational Test Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gifOperations and Support Phase
https://acc.dau.mil/UI/img/bo/plus.gifPackaging Handling Storage and...
https://acc.dau.mil/UI/img/bo/plus.gifPackaging Handling Storage and...
https://acc.dau.mil/UI/img/bo/plus.gifPackaging, Handling, Storage, and...
https://acc.dau.mil/UI/img/bo/plus.gifPackaging, Handling, Storage, and...
https://acc.dau.mil/UI/img/bo/plus.gifPackaging,Handling, Storage &...
https://acc.dau.mil/UI/img/bo/plus.gifPerformance Based Logistics Support
https://acc.dau.mil/UI/img/bo/plus.gifPerformance Metrics
https://acc.dau.mil/UI/img/bo/plus.gifPerformance-Based Agreements
https://acc.dau.mil/UI/img/bo/plus.gifPerformance-Based Support
https://acc.dau.mil/UI/img/bo/plus.gifPhysical Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gifPlan Equipment Publications
https://acc.dau.mil/UI/img/bo/plus.gifPlan for Personnel
https://acc.dau.mil/UI/img/bo/plus.gifPlan Repair Parts
https://acc.dau.mil/UI/img/bo/plus.gifPlan Technical Data
https://acc.dau.mil/UI/img/bo/plus.gifPlan Training Systems
https://acc.dau.mil/UI/img/bo/plus.gifPost Deployment Software Support
https://acc.dau.mil/UI/img/bo/plus.gifPost Fielding Reviews
https://acc.dau.mil/UI/img/bo/plus.gifPost Production Support Analysis - Phase...
https://acc.dau.mil/UI/img/bo/plus.gifPost Production Support Analysis - Phase...
https://acc.dau.mil/UI/img/bo/plus.gifPost-Production Support Plan
https://acc.dau.mil/UI/img/bo/plus.gifPreferred System Concept
https://acc.dau.mil/UI/img/bo/minus.gifPreliminary Design Review
https://acc.dau.mil/UI/img/bo/plus.gifPreliminary System Specification
https://acc.dau.mil/UI/img/bo/plus.gifPre-Planned Product Improvement
https://acc.dau.mil/UI/img/bo/plus.gifProduce Preliminary Technical Manuals
https://acc.dau.mil/UI/img/bo/plus.gifProducibility Engineering Plan
https://acc.dau.mil/UI/img/bo/plus.gifProduct Baseline
https://acc.dau.mil/UI/img/bo/plus.gifProduction and Deployment Phase
https://acc.dau.mil/UI/img/bo/plus.gifProduction Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gifProgram Facility Funds
https://acc.dau.mil/UI/img/bo/plus.gifProgram Management Activities
https://acc.dau.mil/UI/img/bo/plus.gifProvisioning Data
https://acc.dau.mil/UI/img/bo/plus.gifProvisioning Plan
https://acc.dau.mil/UI/img/bo/plus.gifProvisioning Screening
https://acc.dau.mil/UI/img/bo/plus.gifProvisioning Technical Documentation...
https://acc.dau.mil/UI/img/bo/plus.gifPublish DMWR / NMWR
https://acc.dau.mil/UI/img/bo/plus.gifPublish Modification Work Orders
https://acc.dau.mil/UI/img/bo/plus.gifRefine Task Analysis
https://acc.dau.mil/UI/img/bo/plus.gifReliability Centered Maintenance (RCM)...
https://acc.dau.mil/UI/img/bo/plus.gifReliability Centered Maintenance...
https://acc.dau.mil/UI/img/bo/plus.gifReliability Enhancement
https://acc.dau.mil/UI/img/bo/plus.gifReliability-Centered Maintenance...
https://acc.dau.mil/UI/img/bo/plus.gifRemove Obsolete NSNs
https://acc.dau.mil/UI/img/bo/plus.gifRepair Parts and Special Tools List
https://acc.dau.mil/UI/img/bo/plus.gifRepair Parts Concept
https://acc.dau.mil/UI/img/bo/plus.gifRescind Equipment Publications
https://acc.dau.mil/UI/img/bo/plus.gifResident/OJT Training Requirements
https://acc.dau.mil/UI/img/bo/plus.gifRevise PHS&T Guidance
https://acc.dau.mil/UI/img/bo/plus.gifRevise Training Program
https://acc.dau.mil/UI/img/bo/plus.gifSample Data Collection
https://acc.dau.mil/UI/img/bo/plus.gifSchedule Equipment Publications
https://acc.dau.mil/UI/img/bo/plus.gifSecurity Requirements
https://acc.dau.mil/UI/img/bo/plus.gifSelection and Allocation of Repair Parts
https://acc.dau.mil/UI/img/bo/plus.gifSensitivity Analysis
https://acc.dau.mil/UI/img/bo/plus.gifSet System Readiness Objectives (SRO)...
https://acc.dau.mil/UI/img/bo/plus.gifShelf Life
https://acc.dau.mil/UI/img/bo/plus.gifSkills
https://acc.dau.mil/UI/img/bo/plus.gifSoftware Support
https://acc.dau.mil/UI/img/bo/plus.gifSolicitation Documents
https://acc.dau.mil/UI/img/bo/plus.gifSupply Support
https://acc.dau.mil/UI/img/bo/plus.gifSupport Equipment
https://acc.dau.mil/UI/img/bo/plus.gifSupport Facilities 1
https://acc.dau.mil/UI/img/bo/plus.gifSupport Facilities 2
https://acc.dau.mil/UI/img/bo/plus.gifSupport Facilities Annex
https://acc.dau.mil/UI/img/bo/plus.gifSupport Facilities Concept
https://acc.dau.mil/UI/img/bo/plus.gifSupport for Test Equipment and Tools
https://acc.dau.mil/UI/img/bo/plus.gifSupport System Standardization...
https://acc.dau.mil/UI/img/bo/plus.gifSupport System Standardization...
https://acc.dau.mil/UI/img/bo/plus.gifSupport System Tradeoff Analysis
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Analysis
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Assessment - Phase 2
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Assessment - Phase 3
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Integrated Product Team
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Strategy -
https://acc.dau.mil/UI/img/bo/plus.gifSupportability Test, Evaluation, and...
https://acc.dau.mil/UI/img/bo/plus.gifSustain the System to Achieve Materiel...
https://acc.dau.mil/UI/img/bo/plus.gifSustainment Metrics
https://acc.dau.mil/UI/img/bo/plus.gifSustainment Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gifSystem Concept Review
https://acc.dau.mil/UI/img/bo/plus.gifSystem Engineering Activities
https://acc.dau.mil/UI/img/bo/plus.gifSystem Functional Baseline
https://acc.dau.mil/UI/img/bo/plus.gifSystem Functional Review
https://acc.dau.mil/UI/img/bo/plus.gifSystem MANPRINT Management Plan
https://acc.dau.mil/UI/img/bo/plus.gifSystem Performance Specification
https://acc.dau.mil/UI/img/bo/plus.gifSystem Requirements Review
https://acc.dau.mil/UI/img/bo/plus.gifSystem Specification
https://acc.dau.mil/UI/img/bo/plus.gifSystem Support Package
https://acc.dau.mil/UI/img/bo/plus.gifSystem Training Plan
https://acc.dau.mil/UI/img/bo/plus.gifSystem Verification Review
https://acc.dau.mil/UI/img/bo/plus.gifTarget Audience Description
https://acc.dau.mil/UI/img/bo/plus.gifTask Analysis -
https://acc.dau.mil/UI/img/bo/plus.gifTechnical Baseline
https://acc.dau.mil/UI/img/bo/plus.gifTechnical Data
https://acc.dau.mil/UI/img/bo/plus.gifTechnical Manual Verification Plan
https://acc.dau.mil/UI/img/bo/plus.gifTechnical Reviews
https://acc.dau.mil/UI/img/bo/plus.gifTechnology Development Phase
https://acc.dau.mil/UI/img/bo/plus.gifTechnology Development Strategy
https://acc.dau.mil/UI/img/bo/plus.gifTechnology Refreshment Program
https://acc.dau.mil/UI/img/bo/plus.gifTechnology Risk Reduction Assessment
https://acc.dau.mil/UI/img/bo/plus.gifTest and Evaluation Master Plan -
https://acc.dau.mil/UI/img/bo/plus.gifTest Equipment and Tool Concept
https://acc.dau.mil/UI/img/bo/plus.gifTest Equipment and Tools
https://acc.dau.mil/UI/img/bo/plus.gifTest Program Sets
https://acc.dau.mil/UI/img/bo/plus.gifTest Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gifTotal Package Fielding
https://acc.dau.mil/UI/img/bo/plus.gifTrained Personnel
https://acc.dau.mil/UI/img/bo/plus.gifTraining — Program of Instruction
https://acc.dau.mil/UI/img/bo/plus.gifTraining and Training Support
https://acc.dau.mil/UI/img/bo/plus.gifTraining Concept
https://acc.dau.mil/UI/img/bo/plus.gifTraining for Test
https://acc.dau.mil/UI/img/bo/plus.gifTraining Materials Determination
https://acc.dau.mil/UI/img/bo/plus.gifTransportability Report
https://acc.dau.mil/UI/img/bo/plus.gifType Classification
https://acc.dau.mil/UI/img/bo/plus.gifType II Business Case Analysis
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Analysis of Alternatives
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Computer Resource Management Plan
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Disposal Plan
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Item Unique Identification (IUID)...
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Life Cycle Sustainment Plan (...
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Market Research
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Materiel Fielding Plan
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Modification Table of...
https://acc.dau.mil/UI/img/bo/plus.gifUpdate National Stock Numbers (NSN)
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Provisioning Data
https://acc.dau.mil/UI/img/bo/plus.gifUpdate System Training Plan (STRAP)
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Systems Engineering Plan -...
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Systems Engineering Plan -...
https://acc.dau.mil/UI/img/bo/plus.gifUpdate TEMP
https://acc.dau.mil/UI/img/bo/plus.gifUpdate TO&E
https://acc.dau.mil/UI/img/bo/plus.gifUpdate Transportability Report
https://acc.dau.mil/UI/img/bo/plus.gifUse Study
https://acc.dau.mil/UI/img/bo/plus.gifValidate Computer Support
https://acc.dau.mil/UI/img/bo/plus.gifValidate Facility Requirements
https://acc.dau.mil/UI/img/bo/plus.gifValidate MAC
https://acc.dau.mil/UI/img/bo/plus.gifValidate MANPRINT
https://acc.dau.mil/UI/img/bo/plus.gifValidate Packaging Handling Storage &...
https://acc.dau.mil/UI/img/bo/plus.gifValidate Preliminary Technical Manuals
https://acc.dau.mil/UI/img/bo/plus.gifValidate RCM
https://acc.dau.mil/UI/img/bo/plus.gifValidate Repair Parts
https://acc.dau.mil/UI/img/bo/plus.gifValidate Training Systems
https://acc.dau.mil/UI/img/bo/plus.gifVerify DMWR/NMWR
https://acc.dau.mil/UI/img/bo/plus.gifVerify Equipment Publications