[SOE LETTERHEAD]

 

August 8, 2005

 

The Honorable A. J. Eggenberger

Chairman

Defense Nuclear Facilities Safety Board

625 Indiana Avenue, NW, Suite 700

Washington, D.C. 20004

 

Dear Mr. Chairman:

 

Enclosed is the Final Report to the Defense Nuclear Facilities Safety Board (Board) on Recommendation 99-1, which provides a summary of actions taken by the Department to resolve the issues contained in the Board’s August 1999 Recommendation 99-1, Identification of Issues Needing Resolution to Ensure the Long-Term Safety of Pits at Pantex.

 

The Department has implemented corrective actions to address the issues identified in Recommendation 99-1 and as of June 30, 2005, has completed repackaging more than 97 percent of the pits identified in the Secretary’s February 2000 implementation plan.  Repackaging of remaining pits is scheduled to be complete by September 30, 2005.

 

Major corrective actions implemented as a result of Recommendation 99-1 include:

 

 

These actions have resulted in significant improvement to the Department’s ability to ensure safe handling and storage of special nuclear material at Pantex.  The Department welcomes the Board’s ongoing oversight and requests the Board to consider closing Recommendation 99-1.

 

If you have any questions, please contact Mr. Thomas P. D’Agostino, Acting Deputy Administrator for Defense Programs, at (202) 586-2179.

 

Sincerely,

 

Samuel W. Bodman

 

Enclosure

 

cc w/enclosure:

M. Whitaker, DR-1