[DNFSB
LETTERHEAD]
March 28, 2005
The Honorable Linton Brooks
Administrator
National Nuclear Security
Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-0701
Dear Ambassador Brooks:
On July 1, 2003, the Defense Nuclear
Facilities Safety Board (Board) sent you a letter relaying observations related
to electrical and lightning protection systems for several facilities at the
Nevada Test Site (NTS). In your response
of May 14, 2004, you presented a reasonable approach to addressing many of the
issues raised in the Board’s letter. Recently, the Board’s staff conducted a review
of the status of these issues. Enclosed
for your information and use, as appropriate, is a report prepared by the Board’s
staff that provides observations on the actions taken to date.
The Board is also concerned
about the slow progress in developing and moving forward with a defined action
plan for addressing known problems with G-tunnel, the NTS facility proposed for
handling damaged or improvised nuclear devices under certain emergency circumstances.
Although the Nevada Site Office (NSO)
has initiated actions to address some of the specific issues raised by the
Board with respect to the ventilation system for G-tunnel, numerous issues
noted by the Board or by NNSA and its contractors remain unresolved.
NNSA
needs to move
forward aggressively to ensure the adequacy of G-tunnel for its mission. Accordingly, pursuant to 42 U.S.C. §2286b(d),
the Board requests within 120 days that NNSA identify the desired conditions
of readiness for G-Tunnel, including facility and equipment improvements, and
provide its plan and schedule to establish those conditions. In addition, the Board asks to be kept
informed regarding the status of actions to address the other issues noted in
the enclosed report.
Sincerely,
John T. Conway
Chairman
c: Mr. Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff
Issue Report
MEMORANDUM FOR: J. K. Fortenberry, Technical Director
FROM: A. Gwal
SUBJECT: Electrical and Lightning
Protection Systems at the Nevada Test Site
This report documents a review
of electrical and lightning protection systems at the Nevada Test Site (NTS). Members of the staff of the Defense Nuclear
Facilities Safety Board (Board) J. Deplitch, A. Gwal, and W. White visited NTS
January 25–27,
2005, to review electrical and lightning protection systems for the U1a
Complex, Device Assembly Facility (DAF), G-Tunnel, Joint Actinide Shock Physics
Experimental Research Facility, and Radiological Waste Management Complex
(RWMC).
Background. On July 1, 2003, the Board sent a letter to the National
Nuclear Security Administration (NNSA) identifying issues related to the
electrical and lightning protection systems in the U1a Complex, DAF, G-Tunnel,
and Joint Actinide Shock Physics Experimental Research Facility at NTS. In May 2004, nearly a year after the Board’s
letter, NNSA responded by committing to address many of these issues. The staff’s review in January 2005 was conducted
in part to follow up on NNSA’s commitments. The staff found that, with some exceptions,
little progress had been made in addressing issues raised by the Board in its
July 2003 letter.
Ula Complex. The Board raised issues regarding the need to ensure that
certain activities conducted at Ula are adequately protected from the hazards
posed by lightning. In response, NNSA
committed to several actions, most of which were completed prior to NNSA’s May
2004 response. These actions included
adding Ula to the NTS Hazardous Weather Notification List; notifying Ula of all
lightning strikes within 10 miles of the complex, regardless of ongoing
activities; and revising and updating the Lightning-Personnel Safety procedure
(OP-2003.009).
NNSA also noted in its May 2004
response that the “Safety Evaluation Report SER for the Los Alamos National
Laboratory and Lawrence Livermore National Laboratory Subcritical Experiment
Bounding Hazard Analysis and Technical Safety Requirements” established a condition
of approval requiring that a safety-significant lightning protection design
feature be developed for above-ground delivery of subcritical experiments to
the Ula Complex. The development of such
a safety-significant design feature has not been accomplished, and Nevada Site
Office (NSO) personnel were unaware of any ongoing effort to that end.
The Board also raised issues
concerning the potentially excessive combustible loading represented by legacy
diagnostic and power cables within the Ula Complex. NNSA committed to completing a study to
address the probability of a fire within the Ula Complex leading to a fire in
the legacy cables. This study was
finalized 5 days before the staff’s review began in January 2005, but
does not appear to have been changed significantly since NNSA discussed the report
in its May 2004 response to the Board. The study concludes that the cumulative, conditional
probability of an accident involving a load haul dump (LHD), used for
underground earth moving, is about the order of magnitude of 1 x 10-2
per year.
Operational history for 2004
indicated at least five incidents associated with LHDs, one of which involved
the LHD rolling over and leaking fuel oil. The frequency and significance of these events
were significant enough to warrant a stand-down of LHD operations in 2004. The report also discounts the probabilities of
fires from cable failures.
The Board’s staff concluded that
the study had likely underestimated the frequency of fires in the legacy cables.
As a result, the staff believes it would
be advisable for NNSA to consider additional measures to either prevent or
mitigate the hazards associated with this scenario. In particular, NNSA ought to consider
implementing a policy to remove existing legacy cabling, particularly that associated
with completed activities, to limit the growth of the combustible loading in
the Ula Complex. It would be advisable
as well to consider implementing additional controls when LHDs are operated in
the vicinity of legacy cabling (e.g., applying fire-retardant coatings or wraps
on the bundle of cables along frequently traveled routes or establishing
temporary fire watches).
The Board’s staff also reviewed
the list of cables in the report and observed the presence of several power
cables in the bundles of legacy cables. Power cables are capable of initiating fire as
a result of the failure of insulation or jacket material due to age-related
degradation and other electrical short-circuit-related failures. The report assumes that a short-circuit in the
power cable would trip the circuit breaker and stop further heat generation. However, the electrical systems at the Ula
Complex are neither designed nor required to be safety-class. The failure of a breaker could result in the
initiation of a fire. The Board’s staff
believes the use of fire wraps or fire-retardant coatings on the selected
legacy bundles of cables ought to be considered, with particular attention to
the effect of the fire wraps or coatings on the ampacity derating of the power
cables in the legacy bundle and the structural support system.
Device Assembly Facility. The staff agreed to postpone its request to evaluate
electrical and lightning protection systems at DAF during this review so that
DAF personnel could concentrate on a separate, ongoing contractor Operational
Readiness Review related to critical experiment facility activities. The staff was able to walk down the DAF
facility during the review, however, and address the status of other issues
raised in the Board’s previous correspondence. Issues related to the calibration of
protective devices and the pressure alarm systems are considered resolved. The issues discussed below remain open.
Lightning
Protection―In
July 2003, the Board noted the importance of capturing and crediting all
elements of the lightning protection system in the new Documented Safety
Analysis (DSA). NNSA’s response in May
2004 noted that the DAF DSA, which was finalized in September 2003, captured
many of the items of concern to the Board. The staff will review specific applications to
any proposed nuclear explosive operations as part of its review of the safety
basis for the proposed operation.
Uninterruptible
Power Supplies (UPSs)―The
Board’s July 2003 correspondence identified the possibility that inadvertent
actuation of the fire suppression system could impair or disable the
safety-significant UPSs. In its
response, NNSA agreed to initiate a change request to determine the best
method of protecting the UPSs, and to complete the work associated with the change
request by the end of fiscal year 2004. Although DAF has made progress in evaluating potential
modifications to the UPSs to address this issue, the work has not been completed.
Oil-Insulated Transformers―In its July 2003 correspondence,
the Board noted issues associated with the two oil-insulated transformers
located inside the DAF structure. The
DAF transformers are collocated with other electrical equipment, and a fire in
the transformers could impact the facility and this equipment. NNSA agreed to replace the oil in the
transformers with a less flammable fluid by the end of calendar year 2004. This effort is under way, but has not been
completed.
G-Tunnel. The Board raised several issues related to the ventilation
system for G-tunnel in 2003, including damaged power cables and antiquated fan
motor controllers. In response, NNSA
agreed that the long-term operability of the ventilation system is questionable
and committed to evaluating the system thoroughly. NNSA and Bechtel Nevada personnel
provided additional information to the staff during its January review.
To address the issues raised by
the Board, Bechtel Nevada evaluated the ventilation system, and the most
deteriorated ventilation ductwork inside the tunnel is currently being replaced.
The following additional design
modifications to the ventilation system are also under consideration:
Bechtel Nevada personnel also
presented the staff with a list of improvements being considered for electrical
and lightning protection systems in G-Tunnel:
In addition to the improvements
above, the G-Tunnel DSA and Safety Evaluation Report (SER) identify numerous
other improvements for nuclear explosive safety and for lightning, electrical,
fire, and shock impact hazards.
The necessary improvements to
support G-Tunnel readiness appear to exceed available resources. The staff saw no evidence of a comprehensive
project plan that prioritizes potential improvements based on the cost and risk
reduction they would provide. On
February 11, 2005, after the staff review, NSO requested that Bechtel Nevada
develop an implementation plan for the G-Tunnel TSRs. While it is important to begin implementing
the control set in the TSRs, it would also seem prudent to have a project plan
and path forward that integrate all necessary improvements on an appropriately
prioritized basis.
Site-wide Lightning
Detection and Protection. The Board’s July 2003 correspondence
raised two issues related to site-wide lightning detection capabilities at NTS.
First, the staff noted that no technical
basis exists for assuming that the thresholds used for lightning alerts provide
sufficient time to suspend at-risk operations. The staff also noted the need to establish adequate
lightning detection capabilities and documented controls for all facilities for
which lightning could pose an operational hazard.
NNSA’s response did not address
the issue of the technical basis for lightning alert distances. In discussions during the staffs most recent
review, the staff suggested that NTS personnel might consider evaluating
historical alert information to determine the range of advance warning times
being provided by the current alert distances. This would make it possible to either justify
the existing alert distances or provide a basis for alternative distances.
In its response, NNSA did
address the issue of the need to establish clear and well-documented lighting
controls for all impacted facilities. NNSA agreed to establish a Lightning Focus
Group to take several actions, primary among these being to develop a site-wide
policy for lightning safety and to complete a study on the effectiveness of
field mills as part of the lightning detection system at NTS. The Lightning Focus Group appears to consist
of a single NSO person. The policy is
still under development, and no scope of work has been defined for the proposed
study on the effectiveness of field mills.
Radioactive Waste Management
Complex. The staff reviewed the lightning
protection systems at RWMC. While
preparing for the staffs review, RWMC personnel had noted that they were not
conducting required preventive maintenance for the facility’s lightning
protection system. The visual inspection
was conducted just prior to the staffs review, and the electrical inspection is
in progress. Personnel at RWMC committed
to capturing the maintenance requirements in a preventive maintenance procedure.
Summary. Nearly 2 years has passed since the Board’s original review,
and more than 8 months has passed since NNSA’s response. A significant number of the action items to which NNSA
committed
remain unfinished. The staff discussed
this lack of progress with the NSO Manager, who agreed that these actions would
be tracked more closely in the future.
The staff also discussed the
need to develop an approach for lightning protection of G-tunnel before
committing to capital expenditures aimed at improving lightning protection for the
facility. NSO agreed and committed to
including lightning protection enhancements among the list of facility items to
be prioritized and funded as part of the ongoing readiness effort.