FHWA > Programs > Office of Policy > FHWA Strategic Plan > Median Number of Months to Complete an Environmental Impact Statement

Median Number of Months to Complete an Environmental Impact Statement

2D Line Chart titled "Median Number of Months to Complete an Environmental Impact Statement, Fiscal Year 2002-2011." The graph shows the trend in the actual median number of months required to complete all Environmental Impact Statements (EIS) from the Notice of Intent to the Record of Decision, from 72 in FY 2002 to 79 in FY 2011.

Fiscal Year Actual
200272
200366
200455
200560
200660
200771
200860
200984
201071
2011 79

 

Publication Number: FHWA-PL-08-027
October 2008 (Revised July 2012)