Davis-Besse Correspondence Related to NRC Order EA-03-009

Related Information

Reactor Pressure Boundary Integrity Issues for generic information related to the reactor pressure vessel upper and lower head, including generic responses to NRC Bulletin 2002-01 and NRC Order EA-03-009.

On February 11, 2003, NRC issued Order EA-03-009 PDF Icon establishing interim inspection requirements for reactor pressure vessel heads at pressurized water reactors.

On February 20, 2004, NRC issued the First Revised Order EA-03-009 revising the interim inspection requirements for reactor pressure vessel heads at pressurized water reactors.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Plant Name Order Response First Revised Order/