Sign In
Cost Verification Process

The Cost Verification Process for the Slice True-Up Adjustment Charge is a new annual public process developed under the Tiered Rates Methodology (TRM) that will permit Slice customers, other BPA customers, and other interested parties to review the Slice True-Up Adjustment Charge and to assess whether BPA has correctly calculated the amount of each expense or revenue credit subject to the Slice True-Up Adjustment, and whether the final Slice True-Up Adjustment contains only those expenses and revenue credits permitted to be included in, and does not contain any expenses or revenue credits excluded from, the Slice Rate pursuant to the TRM; see section 2.7.5.1 and Attachment A of the TRM.

See our Background page for more information.

Dates (estimated) Agenda
November 21, 2012 or earlier

Notification to Slice Customers of the Slice True-Up Adjustment for the Composite Cost Pool True-Up Table
BPA to post Composite Cost Pool True-Up Table containing actual values and the Slice True-Up Adjustment

FY-12 Composite Cost Pool True-Up Table

December 6th Meeting Materials:

​December 14, 2012

​Deadline for customers to submit questions about actual line items in the Composite Cost Pool True-Up Table with the Slice True-Up Adjustment for inclusion in the Agreed Upon Procedures (AUPs) Performed by BPA external CPA firm (customers have 15 business days following the posting of Composite Cost Pool Table containing actual values and the Slice True-Up Adjustment

Comment Period Closed

​December 31, 2012

​BPA posts a draft list of AUP tasks to be performed (Attachment A does not specify an exact date)

​January 11, 2013

​The Cost Verification Process second comment period is closed.  No AUP tasks for further consideration have been identified. In as much the workshops, comment periods, and draft responses will not be necessary and this concludes the Cost Verification Process for FY 2012.

 
Stay Connected Related Sites