[DOE
LETTERHEAD]
National Nuclear Security AdmINIstratIon
March 9, 2004
The Honorable John T Conway
Chan-man
Defense Nuclear Facilities Safety Board
625 Indiana Avenue, NW
Suite 700
Washington, DC 20004
Dear Mr. Chairman:
In my February 3, 2004, transmission of deliverable
4.6.1 of the Department’s implementation plan for Defense Nuclear Facilities
Safety Board Recommendation 2002-3 we advised you that by February 27, 2004, we
would transmit the Los Alamos National Laboratory (LANL) portion of the commitment
or advise you of the date by which we would provide it.
The initial LANL response received in late
February was incomplete and has been returned to the contractor for further
action. We plan to transmit the LANL
portion of deliverable 4.6.1 by March 31, 2004.
If you have any questions about the National
Nuclear Security Administration (NNSA) portion of commitment 4.6.1 or about our
path forward on NNSA actions under the implementation plan, please contact me
or have your staff contact Jeff Underwood at (301) 903-8303.
Sincerely,
Everet H. Beckner
Deputy Administrator
for
Defense Programs
cc:
M. Whitaker, DR-1
B. Cook, EH-1