REACH 12B ROW for Tribal Trust Lands: Final ROW package received from NN and prepare ROW package and deliver to BIA

REACH 12B ROW for Tribal Trust Lands: Final ROW package received from NN and prepare ROW package and deliver to BIA

Project Title
Navajo Gallup Water Supply Project
Project Id
268153
Type
Activity
Status
Complete
Responsible Agency
Department of the Interior
Responsible Agency POC Name
Michael Braman
Responsible Agency POC Title
Realty Specialist
Responsible Agency POC Email
Mbraman@usbr.gov
Target Start Date
01/08/2013
Target Completion Date
01/16/2013
Actual Start Date
01/11/2013
Actual Completion Date
01/17/2013
Last Updated On
02/19/2013
Description
The Bureau of Reclamation receives consent for Right of Way from the Navajo Nation and prepares the complete Right of Way package to deliver to the Bureau of Indian Affairs for review and authorization for Right of Way.