Clinch River Watershed

FACT SHEET (As of September 2012)

Bookmark and Share Email Print

 Clinch River Watershed

US ARMY CORPS OF ENGINEERS                                                                     BUILDING STRONG®

                                                                           FACT SHEET

                                                                  (As of September  2012)

AUTHORIZATION: House Committee on Transportation and Infrastructure Resolution, Sept. 28, 2000.

TYPE OF PROJECT: General Investigations Ecosystem Restoration Feasibility Study.

LOCATION: Wise and Scott counties in southwestern Virginia.

CONGRESSIONAL INTEREST: Griffith (VA-09), Webb (VA), Warner (VA)

NON-FEDERAL SPONSOR: LENOWISCO Planning District

 

BACKGROUND:

·   LENOWISCO and the Commonwealth of Virginia have signed a Feasibility Cost Share Agreement (FCSA) with the Corps of Engineers to study ecosystem degradation issues within the Guest River Watershed.

 

·   The FCSA was signed in September 2012.

 

·   The Section 905b Preliminary Assessment was approved in September 2004.

 

·   The focus of the study is on ecosystem problems and opportunities in the Guest River Basin. 

 

·   Potential ecosystem restoration solutions to be evaluated during the reconnaissance study include a variety of measures to improve aquatic ecosystem functions and values.

 

IMPORTANCE:

·   The Guest River is the second largest tributary to the Clinch River and the key factor in degraded aquatic ecosystems downstream of the confluence of Clinch and Guest Rivers.

 

·   The Clinch River has been identified by The Nature Conservancy as the number one river for biodiversity in a nationwide study reviewing all rivers in the United States.

 

·   The Clinch River sustains 48 imperiled and vulnerable species, including 29 varieties of rare mussels and 19 species of fish.

 

STATUS: FCSA was signed in September 2012.

 

BUDGET ($): Estimated project costs are shown below.

 

 

Feasibility Phase

Total Estimated Cost

$700,000

     Federal Cost Estimate

350,000

     Non-Federal Cost Estimate

350,000

 

 

Federal Funds Data

 

     Allocation thru FY 2011

$126,182

     Allocation for FY 2012

0

     Balance to Complete

223,818

     President’s Budget for FY 2013

0

SCHEDULE:

 

FY 2011 Completed Work:

FY 2012 Scheduled Work: Feasibility Scoping and FCSA complete.

FY 2013 Scheduled Work: Begin Feasibility Study.

Completion:  Feasibility Study is currently scheduled for 1Q FY15 Completion.

For more information regarding Clinch – Guest River – Ecosystem Restoration, contact Tom Herbert, CELRN-PM-P, phone: (615) 736-7194, email:  thomas.herbert@usace.army.mil.