AUTHORIZATION: House Committee on Transportation and Infrastructure Resolution, Sept. 28, 2000.
TYPE OF PROJECT: General Investigations Ecosystem Restoration Feasibility Study.
LOCATION: Wise and Scott counties in southwestern Virginia.
CONGRESSIONAL INTEREST: Griffith (VA-09), Webb (VA), Warner (VA)
NON-FEDERAL SPONSOR: LENOWISCO Planning District
BACKGROUND:
· LENOWISCO and the Commonwealth of Virginia have signed a Feasibility Cost Share Agreement (FCSA) with the Corps of Engineers to study ecosystem degradation issues within the Guest River Watershed.
· The FCSA was signed in September 2012.
· The Section 905b Preliminary Assessment was approved in September 2004.
· The focus of the study is on ecosystem problems and opportunities in the Guest River Basin.
· Potential ecosystem restoration solutions to be evaluated during the reconnaissance study include a variety of measures to improve aquatic ecosystem functions and values.
IMPORTANCE:
· The Guest River is the second largest tributary to the Clinch River and the key factor in degraded aquatic ecosystems downstream of the confluence of Clinch and Guest Rivers.
· The Clinch River has been identified by The Nature Conservancy as the number one river for biodiversity in a nationwide study reviewing all rivers in the United States.
· The Clinch River sustains 48 imperiled and vulnerable species, including 29 varieties of rare mussels and 19 species of fish.
STATUS: FCSA was signed in September 2012.
BUDGET ($): Estimated project costs are shown below.
|
Feasibility Phase
|
Total Estimated Cost
|
$700,000
|
Federal Cost Estimate
|
350,000
|
Non-Federal Cost Estimate
|
350,000
|
|
|
Federal Funds Data
|
|
Allocation thru FY 2011
|
$126,182
|
Allocation for FY 2012
|
0
|
Balance to Complete
|
223,818
|
President’s Budget for FY 2013
|
0
|
SCHEDULE:
FY 2011 Completed Work:
FY 2012 Scheduled Work: Feasibility Scoping and FCSA complete.
FY 2013 Scheduled Work: Begin Feasibility Study.
Completion: Feasibility Study is currently scheduled for 1Q FY15 Completion.