Skip Navigation Links
About
Power Marketing
Transmission
Newsroom
Contact Us
Training
Energy Services
Renewables
Skip Navigation Links
Transmission
OASIS
Functions
OATT Revisions
Interconnection
Process
Interconnection projects
Contacts
Infrastructure projects

Interconnection

Western accepts requests from electric utilities, firm-power customers, private power developers and independent power generators to interconnect with its transmission system.

Costs

All Western costs associated with the interconnection request are the responsibility of the requesting entity. Advance funds are required before Western performs any studies, design, land acquisition or construction. The contractual agreements will specify the amount of funds required to be advanced. Upon receipt by Western, advance funds will be placed in a cost account for the project. Periodic cost statements will be furnished as studies and work progress.

Steps

There are eight steps in the interconnection process. The process may share steps with the transmission service request process detailed in Western's Open Access Transmission Service Tariff redirecting to a non-governmental site (63 FR 521), the environmental review process outlined in the U.S. Department of Energy's National Environmental Policy Act Implementing Procedures and Western's land acquisition process. Western tries to make the separate processes as seamless as possible.

Projects

There are several interconnection projects currently under construction in Western's territory. Western provides ongoing progress reports for each project and issues a final report with lessons learned when the facility is completed.

Contacts

Entities wishing to interconnect with Western's system should discussed the proposed project with a representative at the Western office that controls the area in which the interconnection will occur.

Interconnecting with other entities
Western is connected with nearly every utility in the Upper Midwest, Rocky Mountain, and Desert Southwest regions and also has extensive transmission resources in California. Use of this transmission, the transmission available to Western under wheeling contracts with other utilities, and access to the DC ties, allows Western to reach resources and transmit power where needed over most of the western United States. Western also interconnects with merchant generators, such as Calpine’s Sutter powerplant