FedBizOpps Tip:
To receive email notification of solicitation actions, click on the hyperlink for a specific project. This will take you to the FedBizOpps website. Select the "Register to Receive Notification" button and follow the steps. Please do this for EACH solicitation you want to track.
Awarded Contracts for Competitive Solicitations
After bids are carefully reviewed and all considerations are accounted for, the lowest bid is confirmed and the project is awarded accordingly. This section lists the name of the project followed by the name of the low bidder and the winning bid amount.
See the Bid Tabs section for unit prices for all bidders.
Are you looking for a specific project?
Please check Upcoming Work, Advertised Projects, Bids Opened, Proposals Received, Awarded Contracts, Awarded IDIQ Contracts, and Cancelled Solicitations.
-
1/31/2013 - MT PRA GLAC 1041(1), Construct Additional Parking Module at the Apgar Transit Center
Contract Awarded to: HK CONTRACTORS, INC.
Amount: $617,945.00
Contract Number: DTFH70-07-D-00009 T-13-001 -
1/15/2013 - AK PRA DENA 10(29), East Fork Toklat River Road Bridge Repairs
Contract Awarded to: CORNERSTONE EQUIPMENT LLC
Amount: $392,754.00
Contract Number: DTFH70-13-C-00002 -
1/11/2013 - AK PRA DENA 10(13), Denali Park Road, Sanctuary Area
Contract Awarded to: TUTKA LLC
Amount: $1,492,310.00
Contract Number: DTFH70-13-C-00003 -
12/10/12 - ID PFH 24(13), Banks-Lowman Rockfall Hazard Mitigation, Phase 1
Contract Awarded to: TK CONSTRUCTION US, LLC
Amount: $3,357,760.76
Contract Number: DTFH70-13-C-00001 -
9/10/2012 - OR PRA CRLA 14(2), Pumice Point Wall Repair
Purchase Order Awarded to: Burkel Construction, Inc.
Amount: $24,360.00
Purchase Order Number: DTFH70-12-P-00074 -
8/27/2012 - MT OMAD 18(50), Minuteman Missile Base Roads
Contract Awarded to: Nelcon, Inc.
Schedule C Amount: $4,123,471.56
Contract Number: DTFH70-11-C-00018 -
08/15/12 - WA FS FSR 99(1), FSR 99 Culvert Replacement and Roadway Repairs
Contract Awarded to: Saybr Contractors, Inc.
Amount: $248,982.00
Contract Number: DTFH70-10-D-00007 T-10-001 T-12-001 -
08/02/12 - AK PFH 43(10) Deweyville Trailhead to Neck Lake Road (Design/Build)
Contract Awarded to: Kiewit Infrastructure West Co
Amount: $41,620,000.00
Contract Number: DTFH70-12-C-00017 -
08/01/12 - AK PRA KEFJ 10(3), EXIT GLACIER ROAD MP 7.0 TO 8.0
Contract Awarded to: Bristol Engineering Services Corporation
Schedule C: $807,082.95
Contract Number: DTFH70-12-C-00016
-
07/31/12 - ID PFH 26(2), Ketchum-Challis Highway
Contract Awarded to: Ascorp Inc., dba Debco Construction
Amount: $1,416,075.00
Contract Number: DTFH70-12-C-00013 -
07/26/12 - MT RRP CMR 108(1), Duck Creek Road Reconstruction
Contract Awarded to: 21 Construction, Inc.
Amount: $298,455.00
Contract Number: DTFH70-12-C-00015 -
07/25/2012 - WA PRA OLYM 12(5), EMERGENCY REPAIRS OF CULVERTS, HURRICANE RIDGE ROAD
Contract Awarded to: NOVA CONTRACTING, INC.
Amount: $318,335.00
Contract Number: DTFH70-12-C-00014 -
06/15/2012 – MT PFH 74(2), North Fork Teton River Road, Phase 2
Contract Awarded to: Ascorp Inc., dba Debco Construction
Amount: $1,736,114.00
Contract Number: DTFH70-12-C-00012 -
06/14/2012 – OR PFH 163(14) Crown Point Viaduct Restoration Project
Contract Awarded to: Tapani Underground, Inc.
Amount: $4,159,596.91
Contract Number: DTFH70-12-C-00011 -
6/04/12 - WY PRA YELL 10(16), Grand Loop Road, Canyon to Tower, Phase II
Contract Awarded to: HK CONTRACTORS INC.
Amount: $17,852,337.45
Contract Number: DTFH70-07-D-00007 T-12-002 -
5/30/12 - OR BLM 2011(2) Grizzly Mountain Road Resurfacing
Contract Awarded to: Robert A. Johnson Trucking
Amount: $675,295.80
Contract Number: DTFH70-12-C-00009 -
5/29/12 - ID PFH 24(10), Davey's Bridge
Contract Awarded to: Legacy Contracting, Inc.
Amount (Schedule A): $3,002,572.30
Contract Number: DTFH70-12-C-00010 -
5/15/12 - WY PRA GRTE 13(7), North Park Road, Jackson Lake Lodge to Leeks Marina Project
Contract Awarded to: HK CONTRACTORS, INC.
Amount: $11,488,160.88
Contract Number: DTFH70-07-D-00007 T-12-001 -
04/30/2012 - OR FS ERFO 101-1202, Wallowa-Whitman 2010 ERFO Repairs
Contract Awarded to: JAL Construction Inc.
Amount: $674,744.36
Contract Number: DTFH70-12-C-00008 -
03/14/2012 - WA PRA MORA 13(5), Stevens Canyon Road, Phase II
Contract Awarded to: TUCCI & SONS, INC.
Amount: $8,910,093.23
Contract Number: DTFH70-12-C-00007 -
02/22/2012 - OR BLM 2011(1), Lower Deschutes Road Resurfacing
Contract Awarded to: HIGH DESERT AGGREGATE & PAVING, INC.
Amount: $1,392,804.00
Contract Number: DTFH70-12-C-00006 -
01/17/2012 - AK PRA DENA 10(31), PORCUPINE FOREST ROAD REPAIR
Contract Awarded to: ALASKA EXCAVATING, LLC.
Amount: $2,739,544.00
Contract Number: DTFH70-12-C-00005 -
01/10/2012 - AK DEN 2009(17), KWETHLUK-JAY HAMMOND ROAD REPAIRS
Contract Awarded to: WEST CONSTRUCTION COMPANY, INC.
Amount: $2,323,147.20
Contract Number: DTFH70-12-C-00002 -
01/09/2012 - AK DEN 2009(10), Tununak ATV Geo-Tech Trail
Contract Awarded to: NORTHERN MANAGEMENT SERVICES, INC.
Amount: $1,513,490.28
Contract Number: DTFH70-12-C-00004 -
01/05/2012 – AK DEN 2009(9), MCGRATH ROADS RECONSTRUCTION
Contract Awarded to: NORTH STAR PAVING & CONSTRUCTION, INC
Amount: $3,667,776.20
Contract Number: DTFH70-12-C-00003 -
12/22/2011 – MT PRA GLAC 202(1), EMERGENCY REPAIR OF UPPER MCDONALD CREEK BRIDGE
Contract Awarded to: HL CONSTRUCTION, INC
Amount: $109,209.47
Contract Number: DTFH70-12-C-00001 -
9/7/2011 - MT OMAD 18(47)& MT PFH 76(1), Minuteman Missile Base Roads & Charles M. Russell Memorial Way
Contract Awarded to: M.K. Weeden Construction, Inc.
Amount: $4,398,109.29
Contract Number: DTFH70-11-C-00018 -
8/24/2011 - WA FS ERFO 091-2003, Tacoma Pass Road FSR 52 Emergency Repairs
Contract Awarded to: Saybr Contractors Inc.
Amount: $229,825.00
Contract Number: DTFH70-10-D-00007, T-11-001 -
08/22/2011- WY PRA GRTE 13(9), North Park Road: Utilities & Slope Stabilization
Contract Awarded to: HK Contractors Inc.
Amount: $745,869.50
Contract Number: DTFH70-07-D-00007, T-11-001 -
08/16/2011 - WA FS ERFO 2009(1)-22(2), Benham Creek Permanent Repairs
Contract Awarded to: CP Construction LLC
Amount: $1,346,889.10
Contract Number: DTFH70-10-D-00004 T-11-001 -
8/8/2011 - WA NPS OLYM 11(1), LAKE CRESCENT RIPRAP BANK ARMORING
Contract Awarded to: Cat Works, LLC
Amount: $603,950.00
Contract Number: DTFH70-10-D-00003 T-11-001 -
08/01/2011 - AK PFH 40-1(1), KAKE TO SEAL POINT ROAD
Contract Awarded to: James Dean Construction, Inc.
Amount: $8,365,366.00
Contract Number: DTFH70-11-C-00016