Related Documents and Other Resources
On this page:
- NRC Correspondence
- NEI 97-06
- Generic Safety Issues (GSI)
- Differing Professional Opinion (DPO) on Steam Generator Issues
- Indian Point 2
- Miscellaneous
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
NRC Correspondence
The following correspondence are related to overall status or closeout of individual steam generator action plan items: Date |
Description |
---|---|
09/25/03 | NRC Letter to D. Grinnell |
05-11-01 | Memo from S. Collins/A. Thadani to W. Travers revising the Steam Generator Action Plan to address Differing Professional Opinion on steam generator tube integrity issues |
03-23-01 | Memo from J. Zwolinski/J. Strosnider/B. Boger/G. Holahan to B. Sheron/R. Borchardt revising the Steam Generator Action Plan and documenting completion of Item Nos. 1.1, 1.2, 1.3, 1.4, 1.7, 1.8, 1.15, 2.1, and 2.2 |
11-16-00 | Memo from B. Sheron/J. Johnson to S. Collins issuing the "Steam Generator Action Plan" |
NEI 97-06
The following documents relate to the NRC review of industry initiative NEI 97-06 to develop an improved regulatory framework for maintaining steam generator tube integrity.
Date |
Description |
---|---|
09-10-04 | Letter from S. Peters, NRC to Southern Nuclear Operating Company - Farley Issuance of Amendment |
03-24-04 | Letter from L. Olshan, NRC to Dusk Energy, Request for Additional Information |
12-23-03 | Letter from B. Sheron, NRC to A. Marion, NEI |
10-10-03 | Letter from L. Olshan, NRC to Duke Energy, Revised Request for Additional information |
09-17-03 | Letter from L. Olshan, NRC to Duke Energy, Request for Additional Information |
07-30-03 | Revised Technical Specificaiton Amendment Request from Duke Power |
06-09-03 | Letter from G. Peterson, Duke Energy to NRC, Response to Requests for Additional Information |
04-30-03 | Letter from L. Olshan, NRC to G. Peterson, Duke Energy "Catawba Nuclear Station, Units 1 and 2 Re:Request for Additional Information" |
03-14-03 | Letter from Tony Pictrangelo, NEI to Dr. W. Beckner, NRC "Forwarding of TSTF, Project Number: 689," (TSTF-449 Rev 0-Steam Generator Tube Integrity) |
02-25-03 | Letter from Duke Energy Corporation to NRC Document Control Desk, "Proposed Technical Specification Announcements" (lead plant application) |
09-09-02 | Letter from NRC to NEI, "NEI Steam Generator Generic License Change Package - Technical Specifications - Revision 6 of Steam Generator Examination Guidelines" |
06-10-02 | Letter from NRC to NEI, "NEI Steam Generator Generic Change Package" |
01-25-02 | Summary of November 28, 2001 Management Meeting with NEI |
01-24-02 | Letter from W. Traverse to G. A. Postolakis, "Proposed Steam Generator Program Guilelines and Associated Gneric License Change Package" |
12-14-01 | Letter from G. Apostolakis (ACRS) to Chairmain Meserve, "Proposed Steam Generator Program Guidelines and Associated Generic License Change Package" |
11-26-01 | Letter from NRC to NEI, "NEI Steam Generator Generic Change Package - Inspection Interval Issue" |
11-02-01 | Letter from NEI to NRC, "Industry Proposal for Steam Generator Inspection Interval Regulatory Controls" |
09-18-01 | NRC Memorandum, "NRC Staff Comments on Steam Generator Inspection Intervals" |
08-02-01 | Letter from NRC to NEI, "NEI Steam Generator Generic Change Package" |
02-07-01 | Letter from NEI to NRC, "NEI 97-06 Steam Generator Program Guidelines, Revision 1" |
01-18-01 | Letter from NRC to NEI, "Revised Industry Steam Generator Program License Change Package" |
12-15-00 | Letter from NRC to NEI, "Indian Point Unit 2 (IP-2) Lessons Learned Task Force Report and the Steam Generator Action Plan" |
12-11-00 | Letter from NEI to NRC, "Revised Industry Steam Generator Program Generic Change Package" |
11-30-00 | Letter from NEI to NRC, "Lessons Learned from Recent Steam Generator Experience" |
11-08-00 | Letter from NEI to NRC, "Interim Guidance for In Situ Pressure Testing" |
10-06-00 | Letter from NEI to NRC, "Insights and Implications of Steam Generator Operating, Inspecting and Maintenance Experience" |
02-04-00 | Letter from NEI to NRC, "Industry Steam Generator Program Generic License Change Package" |
Generic Safety Issues (GSI)
The following documents are related to NRC's generic safety issues in the area of steam generator tube integrity.
- GSI-163 (Multiple Steam Generator Tube Leakage) Description from NUREG-0933
- NUREG-0933, "A Prioritization of Generic Safety Issues"
Differing Professional Opinion (DPO) on Steam Generator Issues
The following documents are related to the NRC's research and developmental work in addressing the issues generated from a DPO on steam generators, and staff activities to integrate the results in the regulatory framework.
Date |
Description |
---|---|
05-21-04 | Letter from M. Bonaca (ACRS) to W. Travers (EDO) |
01-18-02 | Letter from W. Travers (EDO) to G. Apostolakis |
10-18-01 | Letter from G. Apostolakis (ACRS) to Chairman Meserve |
06-14-01 | Letter from G. Apostolakis (ACRS) to Chairman Meserve |
06-01-01 | Memo from W. Travers (EDO) to Chairman Meserve |
06-01-01 | Memo from W. Travers (EDO) to G. Apostolakis (ACRS) |
05-07-01 | Memo from Chairman Meserve to G. Apostolakis (ACRS) |
05-04-01 | Memo from Chairman Meserve to W. Travers (EDO) |
04-24-01 | Memo from J. Hopenfeld (DPO author) to Commission |
03-05-01 | Memo from W. Travers (EDO) to S. Collins (NRR) & A. Thadani (RES), DPO Action Plan Tasking Memo |
03-05-01 | Memo from W. Travers (EDO) to R. Spence (RES) |
03-05-01 | Memo from W. Travers (EDO) to J. Hopenfeld (DPO author), DPO closure |
03-05-01 | Memo from W. Travers (EDO) to J. Larkins (ACRS) |
02-2001 | NUREG-1740, "Voltage Based Alternative Repair Criteria" |
02-01-01 | Letter from D. Powers (ACRS) to W. Travers (EDO), transmitting NUREG-1740 |
DPO Consideration Document |
Indian Point 2
The following historic documents relate to NRC review of the February 15, 2000, Indian Point 2 steam generator tube failure event that led to the development of the steam generator action plan.
Date |
Description |
---|---|
12-15-00 | NRR Response to RES Regarding RES Independent Reviews |
11-03-00 | Staff Review of the OIG Report |
08-29-00 | Office of the Inspector General (OIG) Report related to the Indian Point 2 Steam Generator Tube Failure Event |
10-23-00 | Indian Point 2 Steam Generator Tube Failure Lessons-Learned Report |
Miscellaneous
Date |
Description |
---|---|
08-30-04 | GL2004-01, Requirements for Steam Generator Tube Inspection |
05-16-03 | SECY-03-0080, Steam Generator Tube Integrity (SGTI)-Plans for Revising the Associated Regulatory Framework. |
10-31-01 | NRC Information Notice 2001-16, "Recent Foreign and Domestic Experience with Degradation of Steam Generator Tubes and Integrity" |
03-30-00 | SECY-00-0078, Status and Plans for Revising the Steam Generator Tube Integrity Regulatory Framework" |
Steam Generator Tube Issues | |
11-03-00 | NRC Regulatory Issue Summary 2000-22, "Issues Stemming from NRC Staff Review of Recent Difficulties Experienced in Maintaining Steam Generator Tube Integrity" |