U.S. EPR Application Review Schedule

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the design certification application for the U.S. Evolutionary Power Reactor (U.S. EPR).

Key Milestones Completion Date
Actual - A
Target (Rev 5) - T
Application
Received design certification application 12/11/07 - A
 
Acceptance Review
Federal Register Notice (FRN) published for receipt and availability 01/02/08 - A
FRN published announcing acceptance 02/25/08 - A
Review schedule published (through Phase 6) 03/26/08 - A
 
Safety Review
Phase 1 - Preliminary Safety Evaluation Report (SER) with Requests for Additional Information (RAIs) issued to applicant 01/28/09 - A
Phase 2 - SER with Open Items issued 02/09/12 - A
Phase 3 - Response to ACRS regarding SER with Open Items issued 05/18/12 - A
Phase 4 - Advanced SER with no Open Items issued 03/04/14 - T
Phase 5 - Response to ACRS regarding SER with no Open Items issued 05/14 - T
Phase 6 - Final SER issued 07/14 - T
 
Rulemaking
Issue proposed rule  
Issue final draft rule  
Issue final rule 12/14 - T