Construction News B205 – This is a design/build project. Design is at about 50% complete with expected construction starting in May. Expected completion is summer of 2013 B219 – Canteen Remodel – Construction underway with completion expected end of May
B201 – Ambulatory Care Project – Underway with the demolition of Building 245 and installation of a new parking area. Expected completion is late spring / early summer 2013.
Carpet Replacement Project – Currently working in Building 206, next to be 207 and 208 South. Expected completion is July.
B211 US – Dental Renovation: Construction underway. It is approximately 20% complete. Expected completion is March, 2013.
Fire Wall Penetration Contract – Project is about 90% complete and should be done in November.
B236 - Food Service Construction – Currently out for bid. Expect to award construction project in June with construction starting in early fall. Expected completion is late CY 2013.
Security Upgrades – Primarily associated with the Pharmacy and Residential areas. Project is almost complete. Had one change order that is needed to make the system more robust.
B201 Radiology / Flouro – New unit is in. Some minor cleanup work to be finished to close this out.
B211 Audiology – Construction underway to prepare room for new booths. Expect to be installed and ready for operation in June.
Sidewalks – Project to restart next week along Avenue N. Some temporary closure of ramps will occur at B214 along with restricted parking in that area.
Klamath Falls CBOC - New Building Lease Improvements
Native American Area Upgrade Design – 95% complete
Steam Trap Replacement – Energy Savings – Start April, complete September
Upcoming Projects –
Security Project Phase 2 (new police dispatch center, B208 upgrades, and Infirmary video system) Replace Carpet B213, police area and volunteer area B202 including entrance corridor. Enhance Corridors Phase 2 – B212 through B209 area HVAC System Canteen and Game Room Design for conversion of Boiler Plant to use low pressure steam B201 – Lab and old dental area renovation design Emergency Well Design B223 Basement Clean Up
|