Prepare 100% PS&E

This activitiy consists of the finishing the minor details left incomplete at 95%:

  1. Incorporate comments from 95% review
  2. Develop responses to 95% review comments
  3. Print PS&E package
  4. For A/E designs, verify 95% comments have been incorporated.

Step 1: Incorporate comments from 95% review

Instructions Resources References

Step 2: Develop responses to 95% review comments

Instructions Resources References

Step 3: Print PS&E package

Instructions Resources References
Print PS&E package to PDF and place in file transfer folder.
WFLHD Supplement 9.6.10-1, PS&E Document Handoff Process
Send SCRs to Office Automation

Step 4: For A/E designs, verify 95% comments have been incorporated.

Instructions Resources References