Closed Recommendations
The following are items considered closed related to NTSB Recommendations made to PHMSA Pipeline.
NTSB Classifications:
- CAR - Closed Acceptable Response
- CAA - Closed Acceptable Action
- CAAA - Closed Acceptable Alternative Action
- CAAR - Closed Acceptable Alternative Response
- CNLA - Closed No Longer Applicable
- CUA - Closed Unacceptable Action
- CUR - Closed Unacceptable Response
Recommendation |
Topic |
Date Received |
Date Closed |
R-12-8
|
Pipeline Operator Notification; OAR
|
Mar 2, 2012
|
Sep 20, 2012
|
P-11-13
|
Post Accident Drug & Alcohol Testing; CAA
|
Sep 26, 2011
|
May 1, 2012
|
P-11-01
|
Providing System-Specific Information; CNLA
|
Jun 8, 2011
|
Sep 26, 2011
|
P-11-02
|
Immediate 911 Notifications; CNLA
|
Jun 8, 2011
|
Sep 26, 2011
|
P-10-01
|
Urgent safety recommendations; CAA
|
Jan 3, 2011
|
Feb 14, 2011
|
P-09-03
|
Public Education Program Evaluation; CAR
|
Oct 27, 2009
|
|
P-07-09
|
Operator Regulations; CAA
|
Jun 25, 2007
|
Sep 18, 2009
|
P-07-07
|
Operator Regulations; OAR
|
Jun 25, 2007
|
Feb 14, 2011
|
P-07-08
|
Emergency Response; OAR
|
Jun 25, 2007
|
Feb 14, 2011
|
P-07-01
|
Emergency Response; CAA
|
Jun 7, 2007
|
Mar 17, 2008
|
P-05-02
|
Pipeline Security; CAA
|
Dec 23, 2005
|
Apr 28, 2010
|
P-05-01
|
Pipeline Technology (SCADA screens); CAA
|
Dec 23, 2005
|
Apr 28, 2010
|
P-05-05
|
Pipeline Technology; CAAA
|
Dec 23, 2005
|
May 6, 2010
|
P-05-03
|
Pipeline Technology (leak events); CAA
|
Dec 23, 2005
|
Apr 28, 2010
|
P-05-04
|
Fatigue (liquid accident reporting form); CAA
|
Dec 23, 2005
|
Apr 6, 2010
|
P-04-08
|
Glenpool - Breakout Tanks; CAAA
|
Nov 4, 2004
|
May 18, 2005
|
P-04-07
|
Glenpool - Emergency Response; CAAA
|
Nov 4, 2004
|
May 3, 2005
|
P-04-02
|
Cohasset - Pipeline Integrity; CAA
|
Jul 1, 2004
|
Jan 10, 2011
|
P-03-03
|
Carlsbad - Pipeline Technology (Internal Corrosion); CAA
|
Feb 27, 2003
|
Aug 21, 2005
|
P-03-02
|
Carlsbad - Integrity Management; CAA
|
Feb 27, 2003
|
Apr 21, 2004
|
P-03-01
|
Carlsbad - Pipeline Technology (Internal Corrosion); CAA
|
Feb 27, 2003
|
Sep 20, 2007
|
P-02-02
|
Chalk Point - Damage Prevention; CAA
|
Oct 11, 2002
|
Dec 10, 2002
|
P-02-05
|
Bellingham - Pipeline Technology (SCADA); CAA
|
Oct 11, 2002
|
Mar 3, 2004
|
P-02-04
|
Bellingham - Pipeline Technology (Relief Valve); CAA
|
Oct 11, 2002
|
May 3, 2006
|
P-02-01
|
Chalk Point - Pipeline Technology (Wrinkle Bends); CAA
|
Aug 2, 2002
|
Nov 28, 2006
|
P-01-01
|
South Riding - Damage Prevention; CAA
|
Jun 22, 2001
|
Apr 15, 2004
|
P-99-12
|
Fatigue (Hours of Service); CAAA
|
Jun 1, 1999
|
Apr 28, 2010
|
P-98-30
|
Reedy River - Fatigue (Controller Shifts); CAAA
|
Nov 18, 1998
|
May 3, 2006
|
P-98-02
|
Plastic Pipe; CAA
|
Apr 30, 1998
|
Feb 3, 2010
|
P-90-29
|
Damage Prevention; CAA
|
Oct 1, 1990
|
Jul 1, 2008
|
|
|