Standard Permit

 

A Standard Permit is required when a proposed project does not meet the criteria to qualify for a General Permit, Nationwide Permit, or Letter of Permission. A Standard Permit usually has a 21-day comment period under public noticing, though it can be as short as 15 days or up to 30 days. A copy of the permit drawings and a description of the project are mailed out to the adjacent property owners and the applicant and their consultant. All other interested parties have to access pending public notices from the web. Processing time for these types of permits is usually 60 to 120 days from the receipt of a complete application in non-controversial projects. Controversial or larger projects may take longer.