Rock Creek and Potomac Parkway from P Street to Beach Drive - PRA-ROCR 3A6
District of Columbia
Reconstruction and Rehabilitation of Rock Creek and Potomac Parkway from P Street to Beach Drive
This section will be updated on a weekly basis. Work for February 16, to February 23, 2012
Traffic Control/Weekend and Night Work
|
General Project Description
Pavement reconstruction, rehabilitation, and resurfacing for approximately 1.2 miles of the Rock Creek and Potomac Parkway from Beach Drive to the P Street Bridge. This work includes aggregate base, Superpave asphalt concrete pavement, concrete curb and gutter, steel backed timber guardrail, lighting, and other miscellaneous work.
Design/Construction Schedule:
Construction/Traffic Control will take place over 7 phases. Phase 1 and Phase 2 involve the reconstruction of the intersecting roads Shoreham Drive, Cathedral Avenue, and the Rock Creek Parkway. Phase 1 work began on November 15, 2010. When Phases 1 and 2 are complete, Shoreham Drive and Cathedral Avenue will be fully opened to traffic. Any motorists travelling through this work area should expect to be delayed.
ROCR 3A6 Phase I
This project was awarded on August 11, 2010. Â Construction began November 15, 2010. Expected completion is summer 2013.