Project Eagle
A little Colorado snowstorm has not slowed down construction at the Replacement Hospital!
If you’d like to see more current pictures of the construction, go to our Facebook page at https://www.facebook.com/DenverVAMC.
FAST FACTS ON CONSTRUCTION:
- Over 10,000 cubic yards of structural concrete have been poured on-site, which is only about 10% of the total
- 73% of all drilled piers have been placed
- Inpatient Building South has 95% of its steel in place
- Inpatient North has just begun and has about 10% of its steel erected
- About 1,300 tons of structural steel has been erected overall
- Pre-cast concrete erection at the Parking Staff North building is 95% complete
- Overall construction completion is now at 15.1%.
|