A little Colorado snowstorm has not slowed down construction at the Replacement Hospital!  

If you’d like to see more current pictures of the construction, go to our Facebook page at
 https://www.facebook.com/DenverVAMC.

FAST FACTS ON CONSTRUCTION:

  • Over 10,000 cubic yards of structural concrete have been poured on-site, which is only about 10% of the total
  • 73% of all drilled piers have been placed
  • Inpatient Building South has 95% of its steel in place
  • Inpatient North has just begun and has about 10% of its steel erected
  • About 1,300 tons of structural steel has been erected overall
  • Pre-cast concrete erection at the Parking Staff North building is 95% complete
  • Overall construction completion is now at 15.1%.