Contract Details Vicinity Map


Description

SELA-23 - Uptown Napoleon Avenue - Phase 2 - Claiborne to Carondelet
Consists of 4,300 linear feet of three single-barreled, pile-founded concrete box culverts under median along Napoleon Avenue.

The work consists of constructing approximately 4,300 linear feet of three single-barreled, pile-founded concrete box culverts (useable areas of 28 by 10 ft, 24 by 10 ft, and 18 by 10 ft) under the median along Napoleon Avenue, from South Claiborne Avenue to Carondelet Street. The new culverts will parallel an existing box culvert and will tie in to the existing culvert at South Claiborne Avenue designed and built under SELA authority and the culvert to be constructed under the Uptown, Napoleon Avenue Phase 2 contract at Carondelet Street.

SELA-23A - Uptown Napoleon Avenue - Phase 3 - Carondelet to Constance
Consists of constructing 2,800 linear feet of two single-berrreled concrete box culverts under the median along Napoleon Avenue.

The work consists of constructing approximately 2,800 linear feet of two single-barreled concrete box culverts (useable areas of 18 by 10 ft and 14 by 8 ft) under the median along Napoleon Avenue, from Carondelet Street to Constance Street. The new culverts will parallel an existing box culvert and will tie in to the culvert to be constructed under the Napoleon Avenue Phase 1 contract at Carondelet Street and the existing box culvert at Constance Street.


CONTRACT INFORMATION

SELA-23
Contract Award 09-14-2011
Contract Value $54.16M
SELA-23A
Contract Award Q-3-2013
Contract Value $20-50M


CONSTRUCTION ACTIVITIES

SELA-23 - Contract not awarded.

SELA-23A - Contract not awarded.

Vicinity Map

Photos

Uptown Naploleon Avenue
Uptown Naploleon Avenue

Revision Date: Friday, October 19, 2012