CONSTRUCTION ACTIVITIES
LPV-06a.2 - 16 November 2010: Contractor plans to install and test 30" pipe, will remove the last 72" pipe and drive the rest of the H-pile and sheet pile for Monolith 5 and will begin to place rip-rap to fill the hole left from the old gate structure.
|