South Texas Project, Units 1 and 2 – License Renewal Application
On this page:
- Application Information
- License Renewal Review Schedule
- Project Managers for South Texas Project Electric Generating Station, Units 1 and 2
Application Information:
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 10/26/10 | 10/28/10 |
Publish Federal Register Notice (FRN) - LRA receipt and availability | 12/09/10 | 12/09/10 |
Publish FRN -LRA acceptability, environmental scoping period, and opportunity for hearing | 01/13/11 | 01/13/11 |
Publish FRN -intent to conduct environmental scoping | 01/31/11 | 01/31/11 |
Public Meeting -license renewal process and environmental scoping | 03/02/11 | 03/02/11 |
Deadline for filing hearing requests and petitions for intervention | 03/14/11 | 03/14/11 |
Environmental scoping periods ends | 04/01/11 | 04/01/11 |
Audit - scoping and screening methodology | 05/16/11 | 05/20/11 |
Audit - aging management programs (AMPs) | 06/13/11 | 06/24/11 |
Audit - environmental | 07/11/11 | 07/11/11 |
Inspection - scoping, screening, and AMPs | 08/2011 | 08/07/11 |
Issue draft supplemental environmental impact statement (SEIS) | TBD | |
Public Meeting - draft SEIS | TBD | |
Issue safety evaluation report (SER) with open item(s) | TBD | |
End of comment period for the draft SEIS | TBD | |
ACRS subcommittee meeting on SER with open item(s) | TBD | |
Issue final SEIS | TBD | |
Issue SER | TBD | |
ACRS full committee meeting on SER | TBD | |
NRR decision | TBD |
Note: The South Texas Project review schedule was revised as described in the letters below:
- Revised Schedule Letter (September 27, 2012)
- Revised Schedule Letter (August 10, 2012)
- Revised Schedule Letter (May 22, 2012)
- Revised Schedule Letter (March 19, 2012)
- Original Schedule Letter (February 28, 2011)
Project Managers for South Texas Project
South Texas Project, Units 1 and 2 PMs | |
---|---|
License Renewal (Safety) | John Daily |
License Renewal (Environmental) | Tam Tran |
Lead Power Plant | Balwant Singal |
Page Last Reviewed/Updated Thursday, October 11, 2012